FEE SUMMARY
Sarasota Bradenton International Airport
Commercial Apron Expansion/Taxiway R5 Relocation
Design, Permitting & Bidding Services
| Task | Task Description | Fee | Total Hours | Project Manager | Chief Engineer | Senior Engineer | Senior Engineer - KHA | Engineer | Admin - KHA | Designer | Admin | EOR/ Electrical | EOR/ Structural |
|---|
| $250 | $250 | $170 | $202 | $135 | $74 | $105 | $97 | $250 | $250 |
| General Notes - Airfield Electrical | $ 1,040 | 6 | 0 | 0 | 0 | 0 | 4 | 0 | 0 | 0 | 2 | 0 |
| Airfield Signage Modifications | $ 1,945 | 11 | 0 | 0 | 0 | 0 | 7 | 0 | 0 | 0 | 4 | 0 |
| Airfield Signage Details | $ 1,945 | 11 | 0 | 0 | 0 | 0 | 7 | 0 | 0 | 0 | 4 | 0 |
| Airfield Electrical Abbrev/Legend | $ 770 | 4 | 0 | 0 | 0 | 0 | 2 | 0 | 0 | 0 | 2 | 0 |
| Airfield Electrical Demolition Plans | $ 5,645 | 35 | 0 | 0 | 0 | 0 | 27 | 0 | 0 | 0 | 8 | 0 |
| Airfield Electrical Lighting Plans | $ 5,645 | 35 | 0 | 0 | 0 | 0 | 27 | 0 | 0 | 0 | 8 | 0 |
| Airfield Electrical Details | $ 2,890 | 18 | 0 | 0 | 0 | 0 | 14 | 0 | 0 | 0 | 4 | 0 |
| One Line Diagrams | $ 2,945 | 15 | 0 | 0 | 0 | 0 | 7 | 0 | 0 | 0 | 8 | 0 |
| 2.2 | Project Manual and Specifications | $ 7,783 | 42 | 7 | 0 | 0 | 0 | 5 | 0 | 0 | 14 | 8 | 8 |
| 2.3 | Modifications to Standards | $ 4,858 | 28 | 14 | 0 | 0 | 0 | 0 | 0 | 0 | 14 | 0 | 0 |
| 2.4 | Construction Safety and Phasing Plan (CSPP) | $ 7,145 | 39 | 14 | 0 | 0 | 8 | 10 | 0 | 0 | 7 | 0 | 0 |
| 2.5 | Opinion of Probable Construction Costs | $ 12,898 | 85 | 4 | 0 | 0 | 17 | 20 | 0 | 34 | 2 | 4 | 4 |
| 2.6 | Design Review/Predesign Meeting | $ 1,638 | 9 | 5 | 0 | 0 | 0 | 0 | 0 | 0 | 4 | 0 | 0 |
| 2.7 | Engineers Report | $ 3,500 | 14 | 14 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 |
| Sub-Total: | $ 176,631 | 1004 | 152 | 72 | 0 | 99 | 417 | 24 | 77 | 41 | 85 | 37 |
| TASK 3 - FINAL DESIGN |
| 3.1 | Construction Plans | $ 24,684 | 110 | 62 | 32 | 0 | 0 | 0 | 16 | 0 | 0 | 0 | 0 |
| Cover Sheet | $ 450 | 4 | 0 | 0 | 0 | 0 | 1 | 0 | 3 | 0 | 0 | 0 |
| Project Drawing List | $ 1,304 | 10 | 0 | 0 | 0 | 2 | 2 | 0 | 6 | 0 | 0 | 0 |
| Summary of Quantities | $ 3,585 | 29 | 0 | 0 | 0 | 0 | 18 | 0 | 11 | 0 | 0 | 0 |
| Abbreviations/Legend | $ 480 | 4 | 0 | 0 | 0 | 0 | 2 | 0 | 2 | 0 | 0 | 0 |
| Contract Layout Plan | $ 480 | 4 | 0 | 0 | 0 | 0 | 2 | 0 | 2 | 0 | 0 | 0 |
| Airspace Surface Protection Plan | $ 876 | 5 | 0 | 0 | 0 | 3 | 2 | 0 | 0 | 0 | 0 | 0 |
| Phasing Plans | $ 2,427 | 15 | 0 | 0 | 0 | 6 | 9 | 0 | 0 | 0 | 0 | 0 |
| Maintenance of Traffic Plans | $ 2,427 | 15 | 0 | 0 | 0 | 6 | 9 | 0 | 0 | 0 | 0 | 0 |
| Boring Log and Pvmt. Cores | $ 460 | 3 | 0 | 1 | 0 | 0 | 0 | 0 | 2 | 0 | 0 | 0 |
| Subsurface Utility Data | $ 460 | 3 | 0 | 1 | 0 | 0 | 0 | 0 | 2 | 0 | 0 | 0 |
| Existing Conditions/Survey | $ 1,214 | 8 | 0 | 0 | 0 | 2 | 6 | 0 | 0 | 0 | 0 | 0 |
| Erosion and Sed. Control Plan | $ 815 | 5 | 0 | 2 | 0 | 0 | 0 | 0 | 3 | 0 | 0 | 0 |
| Erosion and Sed. Control Details | $ 710 | 4 | 0 | 2 | 0 | 0 | 0 | 0 | 2 | 0 | 0 | 0 |
| Site Demolition Plans | $ 6,071 | 29 | 0 | 0 | 0 | 3 | 9 | 0 | 0 | 0 | 6 | 11 |
| Site Demolition Details | $ 3,539 | 15 | 0 | 0 | 0 | 2 | 1 | 0 | 0 | 0 | 6 | 6 |
| Geometry and Paving Plans | $ 3,237 | 21 | 0 | 0 | 0 | 6 | 15 | 0 | 0 | 0 | 0 | 0 |
| PCC Pavement Jointing Plans | $ 3,777 | 25 | 0 | 0 | 0 | 6 | 19 | 0 | 0 | 0 | 0 | 0 |