| Task | Task Description | Fee | Total Hours | Project Manager | Chief Engineer | Senior Engineer | Senior Engineer - KHA | Engineer | Admin - KHA | Designer | Admin | EOR/ Electrical | EOR/ Structural |
|---|
| $250 | $250 | $170 | $202 | $135 | $74 | $105 | $97 | $250 | $250 |
| TASK 1 - PRELIMINARY PROJECT ENGINEERING ACTIVITIES |
| 1.1 | Data Collection & Conduct Visual Site Reconnaissance | $ 5,705 | 29 | | 2 | | | 4 | 2 | 4 | 1 | 16 | |
| 1.2 | Plan and Coordinate Design Survey and Design Geotech | $ 2,342 | 12 | 4 | 2 | | | | 2 | | 2 | | 2 |
| Sub-Total: | $ 8,047 | 41 | 4 | 4 | 0 | 0 | 4 | 4 | 4 | 3 | 16 | 2 |
| TASK 2 - PRELIMINARY DESIGN |
| 2.1 | Construction Plans | $ 37,276 | 166 | 94 | 48 | 0 | 0 | 0 | 24 | 0 | 0 | 0 | 0 |
| Cover Sheet | $ 690 | 6 | 0 | 0 | 0 | 0 | 2 | 0 | 4 | 0 | 0 | 0 |
| Project Drawing List | $ 1,784 | 14 | 0 | 0 | 0 | 2 | 4 | 0 | 8 | 0 | 0 | 0 |
| Summary of Quantities | $ 5,430 | 44 | 0 | 0 | 0 | 0 | 27 | 0 | 17 | 0 | 0 | 0 |
| Abbreviations/Legend | $ 750 | 6 | 0 | 0 | 0 | 0 | 4 | 0 | 2 | 0 | 0 | 0 |
| Contract Layout Plan | $ 750 | 6 | 0 | 0 | 0 | 0 | 4 | 0 | 2 | 0 | 0 | 0 |
| Airspace Surface Protection Plan | $ 1,348 | 8 | 0 | 0 | 0 | 4 | 4 | 0 | 0 | 0 | 0 | 0 |
| Phasing Plans | $ 3,506 | 22 | 0 | 0 | 0 | 8 | 14 | 0 | 0 | 0 | 0 | 0 |
| Maintenance of Traffic Plans | $ 3,506 | 22 | 0 | 0 | 0 | 8 | 14 | 0 | 0 | 0 | 0 | 0 |
| Boring Log and Pvmt. Cores | $ 460 | 3 | 0 | 1 | 0 | 0 | 0 | 0 | 2 | 0 | 0 | 0 |
| Subsurface Utility Data | $ 460 | 3 | 0 | 1 | 0 | 0 | 0 | 0 | 2 | 0 | 0 | 0 |
| Existing Conditions/Survey | $ 1,484 | 10 | 0 | 0 | 0 | 2 | 8 | 0 | 0 | 0 | 0 | 0 |
| Erosion and Sed. Control Plan | $ 1,420 | 8 | 0 | 4 | 0 | 0 | 0 | 0 | 4 | 0 | 0 | 0 |
| Erosion and Sed. Control Details | $ 1,210 | 6 | 0 | 4 | 0 | 0 | 0 | 0 | 2 | 0 | 0 | 0 |
| Site Demolition Plans | $ 8,948 | 43 | 0 | 0 | 0 | 4 | 14 | 0 | 0 | 0 | 8 | 17 |
| Site Demolition Details | $ 4,674 | 20 | 0 | 0 | 0 | 2 | 2 | 0 | 0 | 0 | 8 | 8 |
| Geometry and Paving Plans | $ 4,586 | 30 | 0 | 0 | 0 | 8 | 22 | 0 | 0 | 0 | 0 | 0 |
| PCC Pavement Jointing Plans | $ 5,531 | 37 | 0 | 0 | 0 | 8 | 29 | 0 | 0 | 0 | 0 | 0 |
| PCC Jointing Details | $ 944 | 6 | 0 | 0 | 0 | 2 | 4 | 0 | 0 | 0 | 0 | 0 |
| Paving Elevation Plans | $ 5,261 | 35 | 0 | 0 | 0 | 8 | 27 | 0 | 0 | 0 | 0 | 0 |
| Pavement Sections | $ 944 | 6 | 0 | 0 | 0 | 2 | 4 | 0 | 0 | 0 | 0 | 0 |
| Cross Sections | $ 1,890 | 14 | 0 | 0 | 0 | 0 | 14 | 0 | 0 | 0 | 0 | 0 |
| Grading and Drainage Plans | $ 5,590 | 38 | 0 | 4 | 0 | 0 | 34 | 0 | 0 | 0 | 0 | 0 |
| Drainage Profiles | $ 3,294 | 20 | 0 | 4 | 0 | 2 | 14 | 0 | 0 | 0 | 0 | 0 |
| Grading and Drainage Details | $ 2,349 | 13 | 0 | 4 | 0 | 2 | 7 | 0 | 0 | 0 | 0 | 0 |
| Drainage Structure Details | $ 6,640 | 33 | 0 | 2 | 0 | 0 | 14 | 0 | 0 | 0 | 17 | 0 |
| Pavement Marking Plans | $ 3,506 | 22 | 0 | 0 | 0 | 8 | 14 | 0 | 0 | 0 | 0 | 0 |
| Pavement Marking Details | $ 1,753 | 11 | 0 | 0 | 0 | 4 | 7 | 0 | 0 | 0 | 0 | 0 |