Baggage Handling System Project
The Baggage Handling System Project will consolidate the three-existing mini-inline systems into one fully inline system. This project will allow all bag belts in ticketing to feed to one checked baggage inspection room, and will allow for redundant screening machines. VTC was ranked first at the August Board meeting and a contract has been executed for the initial phase of work. VTC has prepared and submitted an application package to seek funding from TSA.
Security Checkpoint Modifications Project
The Security Checkpoint Modifications Project will modify the layout of the existing four lanes to improve the efficiency, prepare for an additional lane, and expand space between lanes to accommodate future CT Machines. This project has been designed and construction contract has been executed. Contractor is substantially complete; and staff is working to close project out.
SRQ Restroom Renovation Project
The SRQ Restroom Renovation Project will modify the existing restrooms making each public restroom within the terminal touchless. It will also relocate the trash receptacles under the sink to eliminate water from the floors and make cleaning quicker and easier for janitorial staff. This project has been designed and advertised for informal bids. The bid opening for this project is July 1, 2020. Stellar Development was the low bid, and was approved by Board at the Special Board Meeting in July. Contractor has received permits and is waiting delivery of material. Contractor has begun on the initial phase of the work.
Whitfield Driveway Removal Project
The Whitfield Driveway Removal project removes concrete driveways remaining on SRQ property that were acquired during the Noise Abatement Project. The driveways are mainly located within the Whitfield Ballentine Neighborhood. The project has been awarded to Landmark Construction, and contractor is substantially complete.
PLANNING
Master Plan Update
The Board selected AECOM at the September Board meeting to update the Airport's Master Plan. The Consultant provided their scope for review in early December, and staff has received an Independent Fee Estimate (IFE). Staff has conducted a negotiation meeting and finalized scope/fees, and Board approved at the May Board meeting. AECOM has gathered Airport statistics and other required information, and has submitted their first of six working papers. The forecast and Airport inventory has been submitted to FAA for their approval, and AECOM has completed the Facility Requirements. AECOM is evaluated Alternatives and preparing cost estimates for various alternates. AECOM and staff have prepared initial timeline for improvements, and the financial feasibility study is underway.
➢ Boundary Survey
The Board selected AID at the November Board meeting to conduct a boundary survey and update the Exhibit A for the Airport Layout Plan (ALP). Staff has conducted a negotiation meeting and finalized scope/fees, and Board approved at the May Board meeting. The contract has been executed and AID is completing title work, and has completed 95% of the field survey, and has submitted a preliminary map.
2021 FAA Pre-Application for AIP Funding
Statt has submitted a pre-application for 2021 FAA AIP funding. Staff is requesting funding for two taxiway rehabilitation projects, Taxiway Charlie and Foxtrot.
2021 FDOT JACIP
Staff will be updating the FDOT JACIP for FY 2021-2025, based upon results from the MPU.