7
Primary Canopies and Optional Canopies Geotechnical Services
Tierra Inc Standard Fee Schedule
SRQ Airport Ground Transportation Improvements Tierra Project No. 6511-21-068
Item DescriptionUnitUnit PriceQuantityTotal
Geotechnical Field Investigation
612-Geo Mobilization Drill Rig Truck MountEach$ 350.001$ 350.00
614-Geo Mobilization Mudbug/All Terrain VehicleEach$ 700.00$ -
610-Geo Mobilization Drill Rig Track MountEach$ 3,250.00$ -
418-Geo Drill Crew Support VehicleDay$ 160.004$ 640.00
619-Geo Mobilization Tri-PodEach$ 1,250.00$ -
419-Geo Drilling Crew 2-PersonHour$ 135.00$ -
420-Geo Drilling Crew 3-PersonHour$ 185.00$ -
Geo SPT Truck 0-50 FtLF$ 12.90175$ 2,257.50
Geo SPT Truck 50-100 FtLF$ 17.00$ -
Geo SPT Truck 100-150 FtLF$ 31.00$ -
Geo SPT Truck 150-200 FtLF$ 39.00$ -
478-Geo SPT Truck-Mud Bug 0-50 FtLF$ 15.20$ -
479-Geo SPT Truck-Mud Bug 50-100 FtLF$ 18.10$ -
480-Geo SPT Truck-Mud Bug 100-150 FtLF$ 32.00$ -
481-Geo SPT Truck-Mud Bug 150-200 FtLF$ 42.00$ -
Geo Grout Boreholes- Truck 0-050 FtLF$ 5.25175$ 918.75
Geo Grout Boreholes- Truck 50-100 FtLF$ 7.00$ -
Geo Grout Boreholes- Truck 100-150 FtLF$ 10.25$ -
Geo Grout Boreholes- Truck 150-200 FtLF$ 14.00$ -
440-Geo Grout Boreholes- Truck/Mud Bug 000-050 FtLF$ 6.25$ -
441-Geo Grout Boreholes- Truck/Mud Bug 050-100 FtLF$ 8.00$ -
442-Geo Grout Boreholes- Truck/Mud Bug 100-150 FtLF$ 13.10$ -
443-Geo Grout Boreholes- Truck/Mud Bug 150-200 FtLF$ 18.00$ -
Geo Temp Casing 3" Truck 0-050 FtLF$ 8.50$ -
Geo Temp Casing 3" Truck 50-100 FtLF$ 10.25$ -
Geo Temp Casing 3" Truck 100-150 FtLF$ 12.25$ -
Geo Temp Casing 3" Truck 150-200 FtLF$ 15.00$ -
488-Geo Temp Casing 3" Truck/Mud Bug 000-050 FtLF$ 10.30$ -
489-Geo Temp Casing 3" Truck/Mud Bug 050-100 FtLF$ 14.00$ -
490-Geo Temp Casing 3" Truck/Mud Bug 100-150 FtLF$ 17.50$ -
491-Geo Temp Casing 3" Truck/Mud Bug 150-200 FtLF$ 22.00$ -
401-Geo Auger Borings- Hand & Truck/Mud BugLF$ 10.5040$ 420.00
402-Geo Auger Borings- TrackLF$ 12.00$ -
432-Geo Field Permeability 0-10 Ft (Open - End Borehole Method)Each$ 290.00$ -
Flagman and Barricades 2-Man Crew Own EquipmentDay$ 890.001$ 890.00
Muck Probing Unsuitable Soils 2-Man CrewDay$ 1,080.00$ -
450-Geo Piezometer 2" 000-050 FtLF$ 44.00$ -
445-Geo Grouted Monitor Well 2" 000-050 FtLF$ 6.25$ -
Piezometer Permit Cost ActualEach$ 150.00$ -
403-Geo Backhoe (Owned)Day$ 600.00$ -
416-Geo Dozer (Owned)Day$ 800.00$ -
Site Clearing to Access Boring or Test LocationsHour$ 210.00$ -
407-Geo Chainsaw (Owned)Day$ 28.00$ -
415-Geo Double Ring Infiltration (ASTM D3385)Each$ 525.00$ -
434-Geo Ground Penetrating Radar (GPR)Day$ 2,800.000.5$ 1,400.00
ψ
1