Construction Documents (100%)

Produce detailed construction documents and specifications, as necessary. Typical deliverable will include:

  1. Sign Location Plans
  2. Sign Graphic Layouts*
  3. Sign Mounting Elevations
  4. Sign Fabrication Details
  5. Technical Specifications
  6. *A Sign Message Schedule will be provided only if sign messaging is not included in Sign Graphic Layouts.

Task 2: GTC Building Exterior

Conceptual Design (30%)

Provide design concepts to address the signage requirements as dictated by necessary architectural and messaging considerations. Typical deliverable will include:

  1. Sign Type Location Plans
  2. Sign Design and Message Layout Concepts
  3. Fabrication and Materials Notes

Design Development (60%)

Limited review and comment on 60% deliverable developed by AVCON.

Construction Documents (100%)

Limited review and comment on 100% deliverable developed by AVCON.

MEETINGS / PRESENTATIONS

On-Site Meetings (travel required): None

Project coordination meetings: Up to two (2) video meetings per submittal at 30%, 60%, and 100%.

PROJECT SCHEDULE

Schematic Design:TBD
Design Development:TBD
100% Construction Documents:TBD
Total Project Schedule:TBD

ASSUMPTIONS & CLARIFICATIONS / EXCLUSIONS

Assumptions

  1. All deliverables to be submitted electronically.
  2. Availability of accurate plan documents necessary to complete all required tasks and subtasks for this project.
  3. All destination terminology will be provided to Apple Designs by others.