EXHIBIT A - DESIGNER'S COMPENSATION
PROJECT: SARASOTA BRADENTON INTERNATIONAL AIRPORT GROUND TRANSPORTATION CENTER
PREPARED BY: TRANSYSTEMS CORPORATION DBA TRANSYSTEMS CORPORATION CONSULTANTS
Chief Planner Project Director Transportation Planner Lead Architect Project Architect Senior Architect (H/M/N) Sr. Security Designer Seniority Designer TOTAL S
$300.00 $HR $125.00 $HR $195.00 $HR $150.00 $HR $293.00 $HR $222.00 $HR $183.00 $HR
Manhours Cost Manhours Cost Manhours Cost Manhours Cost Manhours Cost Manhours Cost Manhours Cost Manhours Cost Avg. Hourly Rate
1.0 PROGRAM VERIFICATION
1.1 Transportation Programming 1 $ 300.00 6 $ 750.00 5 $ 5 5 5 5 5 7 $ 1,050.00 $150.00
1.2 Safe Planning 1 $ 2 $ 250.00 5 - 5 5 5 5 5 5 2 $ 250.00 $122.00
1.3 ITS/NEWS ID Control System 1 $ 300.00 5 - 5 - 5 5 5 2 444.00 2 $ 330.00 3 240.00
1.4 Driver's Lounge Programming 1 $ 300.00 5 - 8 $ 1,580.00 8 $ 500.00 5 5 21 $ 3,850.00 $188.07
1.5 MEP Concepts 1 $ - 5 - 5 5 5 5 5 5 5 5 5 5 - #DIV/0!
1.5.1 PAND 1 $ - 5 - 5 5 5 5 5 5 5 5 5 5 - #DIV/0!
1.5.1 Planning 1 $ - 5 - 5 5 5 5 5 5 5 5 5 5 - #DIV/0!
1.5.1 Electrical 1 $ - 5 - 5 5 5 5 5 5 5 5 5 5 - #DIV/0!
1.6 Caropy Architectural Concepts 1 $ 300.00 5 - 8 $ 1,560.00 8 $ 1,200.00 4 $ 5 21 $ 3,060.00 $183.67
1.7 Wayfinding Sponge Concepts 1 $ - 5 - 5 5 5 5 5 5 5 5 5 5 - #DIV/0!
1.7.1 GTC Building Interface 1 $ - 5 - 5 5 5 5 5 5 5 5 5 5 - #DIV/0!
1.7.2 GTC Building External 1 $ - 5 - 5 5 5 5 5 5 5 5 5 5 - #DIV/0!
1.8 Surveying 1 $ - 5 - 5 5 5 5 5 5 5 5 5 5 - #DIV/0!
1.9 Geotechnical 1 $ - 5 - 5 5 5 5 5 5 5 5 5 5 - #DIV/0!
1.10 Landscaping Plant Material Selection 1 $ - 5 - 5 5 5 5 5 5 5 5 5 5 - #DIV/0!
1.11 Ambulite and Lead Surveys 1 $ - 5 - 5 5 5 5 5 5 5 5 5 5 - #DIV/0!
1.12 Meetings 1 $ 300.00 5 - 5 2 $ 300.00 5 - 5 5 3 5 600.00 $200.00
1.13 Cost Engineering 1 - - 5 - 5 5 5 5 5 5 5 5 5 5 - #DIV/0!
2.0 SCHEMATIC DESIGN PHASE (32%)
2.1 OVC/SIC Drawings 1 $ - 5 - 5 5 5 5 5 5 5 5 5 5 - #DIV/0!
2.2 Vehicle TrackingITS Plan 1 $ 300.00 5 - 5 - 5 5 5 10 2,220.00 80 $ 13,200.00 11 2,520.00 $229.09
2.3 Driver's Lounge Plans 1 $ 300.00 5 - 20 $ 3,900.00 40 $ 5,000.00 8 $ 5 69 $ 12,000.00 $173.91
2.4 Caropy Drawings 1 $ 300.00 5 - 20 $ 3,900.00 20 $ 3,000.00 8 $ 5 49 $ 9,000.00 $183.67
2.5 Wayfinding Spings 1 $ - 5 - 5 5 5 5 5 5 5 5 5 5 - #DIV/0!
2.6 Landscape Plans 1 $ - 5 - 5 5 5 5 5 5 5 5 5 5 - #DIV/0!
2.7 Permitting 1 $ - 5 - 5 5 5 5 5 5 5 5 5 5 - #DIV/0!
2.8 Cost Estimales 1 $ - 5 - 5 5 5 5 5 5 5 5 5 5 - #DIV/0!
2.9 Preliminary Technical Specifications (List & Outline) 1 $ - 5 - 5 5 5 5 5 5 5 5 5 5 - #DIV/0!
2.10 Preliminary Calculations 1 $ - 5 - 5 5 5 5 5 5 5 5 5 5 - #DIV/0!
2.11 Meetings 1 $ 300.00 5 8 $ 1,560.00 5 5 5 5 4 888.00 5 13 $ 2,748.00 $211.38
1.0 DESIGN SUBMITTAL PRASE (60%)
3.1 Civil/Ste Drawings 1 $ - 5 - 5 5 5 5 5 5 5 5 5 5 - #DIV/0!
3.2 Vehicle TrackingITS Plan 1 $ 300.00 5 - 40 $ 7,800.00 100 $ 15,000.00 12 $ 2,700.00 5 153 $ 25,800.00 $188.63
3.3 Driver's Lounge Plans 1 $ 300.00 5 - 75 $ 14,820.00 95 $ 14,250.00 12 $ 2,700.00 5 184 $ 32,070.00 $174.29
3.4 Caropy Drawings 1 $ - 5 - 5 5 5 5 5 5 5 5 5 5 - #DIV/0!
3.5 Wayfinding Spings 1 $ - 5 - 5 5 5 5 5 5 5 5 5 5 - #DIV/0!
3.6 Landscape Plans 1 $ - 5 - 5 5 5 5 5 5 5 5 5 5 - #DIV/0!
3.7 Permitting 1 $ - 5 - 5 5 5 5 5 5 5 5 5 5 - #DIV/0!
3.8 Cost Estimates 1 $ - 5 - 5 5 5 5 5 5 5 5 5 5 - #DIV/0!
3.9 Technical Specifications 1 $ - 5 - 5 5 5 5 5 5 5 5 5 5 - #DIV/0!
3.10 Calculations 1 $ 300.00 5 8 $ 1,560.00 5 5 5 5 3 5 5 12 $ 2,526.00 $210.50
3.11 Meeting 1 $ - 5 - 5 5 5 5 5 5 5 5 5 5 - #DIV/0!
4.0 CONSTRUCTION DOCUMENT PHASE (100%)
4.1 Civil/Ste Drawings 1 $ - 5 - 5 5 5 5 5 5 5 5 5 5 - #DIV/0!
4.2 Vehicle TrackingITS Plan 1 $ 300.00 5 - 40 $ 7,800.00 80 $ 12,000.00 8 $ 1,800.00 5 129 $ 21,900.00 $189.77
4.3 Driving Lounge Plans 1 $ 300.00 5 - 60 $ 11,700.00 80 $ 12,000.00 8 $ 1,800.00 5 146 $ 25,800.00 $173.16
4.4 Caropy Drawings 1 $ - 5 - 5 5 5 5 5 5 5 5 5 5 - #DIV/0!
4.5 Wayfinding Spings 1 $ - 5 - 5 5 5 5 5 5 5 5 5 5 - #DIV/0!
4.6 Landscape Plans 1 $ - 5 - 5 5 5 5 5 5 5 5 5 5 - #DIV/0!
4.7 Permitting 1 $ - 5 - 5 5 5 5 5 5 5 5 5 5 - #DIV/0!
4.8 Cost Estimates 1 $ - 5 - 5 5 5 5 5 5 5 5 5 5 - #DIV/0!
4.9 Front End Specifications 1 $ - 5 - 5 5 5 5 5 5 5 5 5 5 - #DIV/0!
4.10 Calculations 1 $ 300.00 5 - 8 $ 1,560.00 8 $ 5 5 3 666.00 5 12 $ 2,526.00 $210.50
4.11 Measuring 1 $ 300.00 5 - 4 $ 780.00 5 5 5 5 5 5 5 - #DIV/0!
4.0 BIDDING PHASE SERVICES 1 $ 300.00 5 - 4 $ 780.00 5 5 5 5 5 5 5 - #DIV/0!
5.1 Bidding Phase Services 1 $ 300.00 5 - 4 $ 780.00 5 5 5 5 5 5 5 - #DIV/0!
TOTALS 16 $ 4,800.00 8 $ 1,000.00 300 $58,500.00 433 $64,550.00 64 $14,400.00 23 $5,106.00 86 $14,190.00 844 $148,756.00 176.25
TOTAL LABOR COST
Copy of Transystems Fee_v7.xls
Page 1