February 19, 2021
TranSystems has developed an architectural concept that alleviates the design concerns of both the Airport and design team. The main concerns are passenger safety, reducing operational conflicts, increased operational efficiency, a new of Driver's Lounge building, and vehicle and bus maneuverability. TranSystems will design a canopy for the new covered shuttle and taxi loop directly adjacent to the terminal, covered queuing options for TNC (such as Lyft and Uber) and Limo pickup, public transportation vehicles (bus) services with an alternate for covered bus stalls, open staging lot for limo and shuttles, Driver's Lounge, and other amenities. TranSystems will also design a 30% design proposal of either an extension to the existing ITS/Vehicle ID system or a replacement system.
The following products will be developed:
Based on Airport count and information TranSystems will gather, we will develop a program determining the number of spaces for all vehicle types in the Ground Transportation Center. Program draft will be issued to AVCON for review by AVCON and Airport Authority. Comments of review will be incorporated into final program report.
○ Produce overall site:
Architectural site plans
After program has been memorialized TranSystems will revise concept site plan as required. Site plan draft will be issued to AVCON for review by AVCON and Airport Authority. Comments of review will be incorporated into final site plan.
o Coordinate desired operations for ITS/Vehicle ID system with Airport and AVCON.
Coordinate desired operations for ITS/Vehicle ID system with Airport and AVCON. Identify locations of Proposed equipment, mounting requirements and infrastructure. A system interconnection diagram indicating network needs and power requirements will be included along with draft specifications and 30% level cost estimate. Typical installation details will be included to support intended application.
o TranSystems will provide full design documents including drawings and specifications as needed for construction of the Driver's Lounge and GTC canopies. Plans and specifications will be issued to AVCON for review by AVCON and Airport Authority at 30, 60, 90 and 100%. Comments of each review will be incorporated into drawings and specifications of the following submittal.
○ Submittal items will include but are not limited to:
Documents for Driver's Lounge:
Documents for Canopies: