2.1 Incorporate final Airport comments from 100% Construction Documents into Bid Documents.
2.2 Provide assistance to the Airport for any revisions required during Bidding Phase to be published with Addendum documents.
2.3 AVCON staff will work closely with the Airport to host the Pre-Bid Conference and provide potential bidders with a tour of the facilities as it relates to the project.
2.4 Answer all potential Bidder questions during Bidding.
2.5 Provide a Bid Evaluation, Bid Tabulation and Recommendation to Award Letter.
2 - Program Verification Reports
PDF of Report
2 – Half-size submittal drawing sets (17x11) 1 – Set of 30% specifications (8.5x11) 1 – Copy of 30% project cost opinion (8.5x11) PDF of all deliverables