SCOPE DETAIL
- i.Major mechanical/electrical systems determined, and their requirements reflected and indicated on the plans including louvers, areaways, and utility entrances
- Scope of Services
November 9, 2021
- j.Rooms named and numbered
- k.Locate exterior and interior doors and windows
- Locate typical and fire rated partition types
- m.All keyed references: match lines, building sections, enlarged plans, etc. keyed notes
- n.Finish floor elevations noted
- o.Expansion joints indicated
- p.Building cores (stairs, elevators, toilets, shafts, etc.) drawn to a larger scale (+/- 1/4"), dimensioned and keyed to larger plans. Enlarged floor plans to contain more detailed information e.g., restrooms with plumbing fixtures, toilet partitions and toilet accessories identified.
- q.Plans and elevations of feature areas (public spaces) drawn to a larger scale (+/- 1/4") with all surfaces shown and materials called out and keyed to larger plans
- r.Demolition plans
- s.Demising wall types, coordinate location with Demolition plans and temporary way finding.
- t.Roof plans
- u.Architectural reflected ceiling plans for all finished spaces
- v.Architectural building elevations
- w.Detailed elevations at a larger scale (+/- 1%) as necessary to explain intent
- x.Major keyed references: match lines, buildings sections, wall sections
- y.Architectural building sections
- z.Representative enlarged Construction details – plan and section
- aa. Long form technical specifications- Draft MLM will work with GS to develop a base specification where MLM can contribute sections specifically and uniquely required in our Tasks and review common specification generated by GS to include requirements, products and execution required to address work in MLM Tasks.
- Scheduling, Phasing, DD Cost Estimate & GMP Reviews: Work with the selected CM to refine the design and construction schedule, and further develop construction phasing plans and provide phasing analyses. Review DD cost estimate prepared by the CM. Assist SRQ and CM on GMP preparation and review for the Civil & Foundation ERP's.
- Construction Documents: The main objective of the Construction Document Phase will be to prepare documents which include sufficient detail required to construct the project.
- Architecture, Interior Design & Wayfinding (MLM-MARTIN):
- a.Coordinate with design team/GS and CM to answer/clarify questions and ensure construction documents are completed and consistent with the criteria established to bid the project. Provide additional information as required to facilitate ‘the ‘buy-out’ of the project following bidding based on CD documents.
- b.Finalize Design Issues
- c.Finalize phasing plans and coordinate schedule requirements with CM and SRO
- d.Based on the Life Safety Plan Coordinate with CM for AHJ requirements for interim Life safety drawings required for permit.