- 2. Scheduling, Phasing & Cost Estimate Reviews: Work with the selected CM to refine the design and construction schedule and develop construction phasing plans and provide phasing analyses. Review cost estimate prepared by the CM.
Design Development Documents and Early Release Packages (ERP)- The Design Development documents will refine and further develop the design concept and space planning established during the Schematic Design Phase.
- Architecture, Interior Design & Wayfinding (GRESHAM SMITH):
- a.Coordinate the development of Civil Site & Utilities ERP submission
- b.Coordinate the development of Structural Foundation ERP submission
- c.Coordinate the Architecture and Interior design with all Engineering systems, including Civil, Structural, Mechanical / Electrical / Plumbing, Communications/I.T., security /CCTV, systems
- d.Define building Materials and develop representative construction details and specification for building systems.
- e.Convey key aspects of the design and building systems in order that SRO's acceptance of the design can be obtained.
- f.Note that design is based upon Option 1 for CEP expansion; if Option 2 is selected by SMAA, additional design will be necessary.
- g.Continue refinement of code and life safety information—attend pre-application meetings with the AHJ
- h.Preliminary development of Technical Specifications
- i.Work with the CM to refine the construction schedule and phasing plans.
- j.Wayfinding- Major wayfinding elements will be identified and incorporated into documents
- i.Develop requirements for new signs.
- ii.Develop requirements for revisions to existing signs.
- iii.Develop requirements for statutory and other room identifications signs.
- iv.Develop requirements for dynamic signs.
- v.Prepare butterfly plans of primary wayfinding elements that show how both the new and existing signage will work and flow.
- Task 2 Design Development Deliverables include:
- a.Architectural building floor plans
- b.Internal partitions located, drawn and located and dimensioned
- c.All casework and other equipment called out on plans
- d.Color and Finish Selections (Interior and Exterior), provide samples for review and approval by SRQ.
- e.Rooms named and numbered
- f.Locate exterior and interior doors and windows
- g.Locate typical and fire rated partition types
- h.All keyed references: match lines, building sections, enlarged plans, etc. keyed notes
- i.Finish floor elevations noted
- j.Expansion joints indicated
- k.Building cores (stairs, elevators, toilets, shafts, etc) drawn to a larger scale (+/- 1/4"), dimensioned and keyed to larger plans. Enlarged floor plans to contain more detailed information e.g. restrooms with plumbing fixtures, toilet partitions and toilet accessories identified.
…
Page | 9