TASK 3: Concourse B Decluttering & Expansion and Main Terminal Vertical Circulation Renovation:
Decluttering of existing Concourse B holdroom areas (Gresham Smith):
Analysis of existing holdrooms, concessions, gate counters, and podiums
Realignment/ modifications to existing gate counters & podiums
Removal of unnecessary fixtures or furnishings
Realignment/rearrangement of seating and circulation to improve efficiency
Additional seating to increase capacity
Expand Concourse B "Bump-out" (MLM-Martin):
2- story additions to existing Concourse B footprint
Includes one additional service elevator for back of house concessions operations
Create additional concessions area
Coordinate with decluttering plan to accommodate new concessions areas and holdroom seating
in Terminal Central Hub (MLM-Martin):
Add two (2) new escalators (16'-0" Vertical rise), adjacent to the existing escalators at the east and west sides:
○ One (1) up from ticketing to transfer level (east)
○ One (1) down to baggage claim from transfer level (west)
Replace two (2) existing escalators (16'-0" Vertical rise)
Renovate second-level concessions area to facilitate the relocation of the Dan McClure Auditorium (SMAA Board Room) from the new GBF expansion to new location