| Project Fee Proposal - JSM & Associates | |||||||||||||||
| SRQ TERMINAL CONCOURSE EXPANSION PROJECT | |||||||||||||||
| SCHEMATIC DESIGN, DESIGN DEVELOPMENT, CONSTRUCTION DOCUMENTS, PERMITTING, AND GMP ASSIST SERVICES | |||||||||||||||
| 11/11/2021 | |||||||||||||||
| SD, DD, CD, Permitting, GMP Assist | Program Manager | Project Manager | BHS Designer | Mechanical Engineer | Elect/Controls Eng | PE | CAD Designer | BHS Installation Specialist | Admin | Fill in staff title | Fill in staff title | Fill in staff title | Fill in staff title | Total | |
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Task Description | |||||||||||||||
| 0a | Task 1 - Conceptual Programming & Layout | ||||||||||||||
| 0b | Flight Demand Analysis | 0 | |||||||||||||
| 0e | System Requirement Definition | 0 | |||||||||||||
| 0d | Equipment Requirement Definition | 0 | |||||||||||||
| 0e | Space Requirements Definition | 0 | |||||||||||||
| 0f | Site Survey | 0 | |||||||||||||
| T1 | Task 2 - Ground Boarding Facility Design, Permit, GMP Assist | ||||||||||||||
| 1 | BHS Equipment Requirement Assessment - Inbound | 8 | 8 | ||||||||||||
| 1a | Site Observation | 16 | 16 | ||||||||||||
| 1b | Modeling | 48 | 8 | 56 | |||||||||||
| 1c | Report | 24 | 40 | 8 | 72 | ||||||||||
| 0 | |||||||||||||||
| 0 | |||||||||||||||
| Subtotal Hours | 8.00 | 24.00 | - | - | 104.00 | - | 16.00 | - | - | - | - | - | - | 152 | |
| Billing Rate | $ 211.30 | $ 190.17 | $ 176.08 | $ 176.08 | $ 162.00 | $ 190.17 | $ 84.52 | $ 154.95 | $ 70.43 | ||||||
| Subtotal Direct Labor | $ 1,690.38 | $ 4,564.04 | $ - | $ - | $ 16,847.50 | $ - | $ 1,352.31 | $ - | $ - | $ - | $ - | $ - | $ - | $ 24,454.23 | |
TOTAL FEE$ 24,454.23