Taxiway Bravo Rehab Slot Pipe

REQUIREMENTS BEFORE WE WILL MOBILIZE:

  • We must have a signed contract.
  • A two week minimum notice is required before mobilization, additional time may be required to produce shop drawings, submittals, manufacture, and procure materials.
  • Outlet piping shall be installed or connection to piping shall be excluded.
  • All conflicting underground utilities must be marked with approximate depth.
  • Survey stake out shall be in place (Typically this would be 10' offsets to center line at both ends and at 50' intervals with a benchmark for grade within 100 feet of the trench).
  • Any equipment or stored materials must be removed from the work area so that we have ample space to perform the work.
  • Prices assume all installations will be based on a mutually agreed upon schedule

For questions regarding this proposal please call Mike Mecsics at 813-484-1251.

ADDITIONAL NOTES:

  • The components used in this quote are Buy America compliant.
  • Prevailing wages have not been considered in this proposal.
  • Insurance limits are included as follows: General liability per project 1M each occurrence and 2M general aggregate, Automotive 1M each occurrence, Umbrella 5M, Workers compensation 1M. Additional limits are available for an additional charge.

Terms & Conditions of Sale:

All work requires approved credit and signed contract or purchase order and signed proposal.

Terms are net 30, paid monthly based on completion with approved credit.

Billing for stored materials shall be allowed.

A copy of this proposal must become a part of any contract agreement.

Retainage is not allowed

By signing this agreement you are certifying that you are authorized to sign and purchase these services and are liable for payment of services. Prices quoted are valid for 60 days from the date of the quote.