Taxiway Bravo Rehab Slot Pipe

COMPANY: NAME: ADDRESS: CITY,STATE,ZIP: E-MAIL:

PHONE:

PROJECT: Taxiway Bravo Rehab Slot Pipe

QUOTE #: INSTREV2

DATE: 10/4/2021

PROJECT SUMMARY:

Install approximately 290' of slotted pipe. Includes setting expansion material, install structural rebar around slotted pipe, install slotted pipe system, place and finish concrete around slotted pipe.

PRICING:

BASE BID: $139,483.73

NOTES:

  • We are assuming normal working hours in this proposal.

.

The outlet pipe is only 4" diameter leaving the question of why a 12" diameter slot drain is being used. Owner may want to consider as a VE the use of a 4", 6", or 8" diameter slot drain to match flow rates required.

WORK INCLUDED:

  • 2 Mobilizations. Additional mobilizations due to factors outside Eric'sons control will require a change order and additional costs.
  • Safety orientation and employee badging.
  • Provide layout for work from provided surveyor stakes/marks.
  • Provide and install 3/4" expansion material. (Note - we don't believe that it should go all the way down as shown in the plans. This can cause settling issues and should be discussed with EOR.)
  • Provide and install a reinforcing cage per plans.

●

  • Provide 12" wide Dura-Trench slotted pipe materials. Trench drain materials shall be per the attached specifications. • Set slotted pipe to finish line and grade. Anchor slotted pipe against movement and floatation during the concrete placement.
  • Place and finish P610 concrete around slotted pipe.
  • Remove any required bracing and formwork.
  • Daily and final clean up of job site to a "broom clean" finish.

WE EXCLUDE THE FOLLOWING:

  • Saw cutting and excavation.
  • Testing (such as compaction, materials testing, etc)
  • Restrooms
  • Trash Dumpsters
  • Traffic control (traffic cones, barracing, etc both during work and after installation to protect from damage to trench and personnel)
  • Dewatering (We will dewater small amounts of rain water if it can be removed by a 2" sump pump in less than 30 minutes. All other pumping of water that is caused by being below water table, equipment dumping into work area, etc. shall be by others)
  • Concrete pumping (all placements are chute pours from ready mix truck)
  • Pipe, sod, asphalt, backfill, and anything not specifically mentioned in our proposal.
  • Sealing of expansion joints