Project Description: Rehabilitation and repair of Taxiway Bravo Description: FDOT Fin. Proj. No. G.L. Acct. No. 3-12-0071-058-2020
Contractor: Ajax Paving Industries of Florida Change Order # 18241-00-000
Address: One Ajax Drive N. Venice, FL 34275 02
ORIGINAL CONTRACT AMOUNT: $ 2,093,373.70
COST OF PREVIOUS CHANGE ORDER: $ 140,337.63
COST OF THIS CHANGE ORDER REVISED CONTRACT AMOUNT: $ 276,139.13
DESCRIPTION OF CHANGE QUANTITY UNIT PRICE TOTAL AMOUNT
Project Title: Taxiway Bravo Rehabilitation Project Date Prepared: AIP No. November 9, 2021
N/A
$ 2,509,850.46
ADD: Labor and Materials to install slotted pipe system per attached detail:
Subject to the conditions set forth below, an equitable adjustment is established as follows:
The contract price is ... The contract time to complete work is ...
Not changed. X Not changed.
X Increased Increased/Decreased
The foregoing is in accordance with your contract dated July 17, 2020 and as listed below:
SIGNATURE TITLE DATE
Owner Representative: Chairman, SMAA
Contractor Ajax Industries of FL
Design Consultant Kimley-Horn
FAA: (if applicable) N/A
FDOT (if applicable) N/A
DISTRIBUTION: Copy for Each Signatory Party, SMAA Finance, SMAA Project File