ItemSpecificationDescriptionUnitQuantityUnit CostAmountFinal QuantityAmountPercentComment
32D-701-5.1c36-inch RCP, Class III, Complete in-placeLF80175.0014,000.0080.0014,000.00100%
33D-701-5.1d36-inch RCP, Class V, Complete in-placeLF68225.0015,300.0024.005,400.0035%Adjusted for field conditions
34D-701-5.1e42-inch RCP, Class IV, Complete in-placeLF248255.0058,280.00272.0063,920.00110%Adjusted for field conditions
35D-701-5.1f48-inch RCP, Class III, Complete in-placeLF140350.0049,000.00144.0050,400.00103%Adjusted for field conditions
36D-701-5.1g48-inch RCP, Class V, Complete in-placeLF64570.0036,480.0024.0013,680.0038%Adjusted for field conditions
37D-701-5.1h60-inch RCP, Class III, Complete in-placeLF2,080350.00728,000.002,096.00733,600.00101%Adjusted for field conditions
38D-701-5.1j60-inch RCP, Class V, Complete in-placeLF2,456650.001,596,400.002,456.001,596,400.00100%
38aD-701-5.1j54-inch RCP, Class III, Complete in-placeLF474350.00165,900.00480.00168,000.00101%Adjusted for field conditions
38bD-701-5.1k54-inch RCP, Class IV, Complete in-placeLF112645.0072,240.00112.0072,240.00100%
39D-705-5.18-inch Perforated Prewrapped PVC Pipe, CompleteLF34025.008,500.00320.008,000.0094%Adjusted for field conditions
40D-751-5.3InletsEA1816,550.00297,900.0023.00380,650.00128%Additional inlets required to adjust pipe routing in the vicinity of failing retaining wall and in areas where underground pipes were found that were not shown on as-built drawings or that could be located from the ground surface in dry areas by the design survey
41D-752-5.2Structural ConcreteCY781,325.00103,350.0078.00103,350.00100%
42D-752-5.3Reinforcing SteelLB3,3001.304,290.003,300.004,290.00100%
43D-755-7.1Pond DewateringEA622,000.00132,000.008.00176,000.00133%One pond in phase 3 and all three ponds in phase 4 met the increased flow criteria to increase the pay item by 50% per pond. During dewatering flows were 150% higher than the project design due to increased rain and deeper scour depths.
44D-756-4.1Gabion Baskets, Including Concrete Aggregate FillEA1,360265.00360,400.001,344.00356,160.0099%Normal variance
45D-757-7.1Zone 1 Graded Aggregate FilterTON2,49045.00112,050.009,060.00407,700.00364%The contractor elected to install geotextile fabric at no cost of the project to use Zone 1 filter material solely, eliminating Zone 2 and3 graded to aggregate filter. The total filter quantity matches the Zone 1 through 3 requirement
46D-757-7.2Zone 2 Graded Aggregate FilterTON3,13045.00140,850.00-0%Refer item 45 above
47D-757-7.3Zone Graded Aggregate FilterTON3,44045.00154,800.00-0%Refer item 45 above
48D-757-7.4Geotextile FabricSY6,3002.3014,490.000.00-0%Refer item 45 above
49T-901-5.1SeedingAC552,200.00121,000.000.00-0%Sodding was substituted for seeding for operational time, access and availability reasons.
50T-904-5.1SoddingSY98,1543.00294,462.00158,890.00476,670.00162%Refer 50 above
51T-905-5.1Topsol (Obtained on site or removed from stockpile)SY17,7707.50133,275.0017,895.00134,212.50101%Normal variance
52L-108-5.1Cable TrenchingLF2,6053.408,857.002,605.008,857.00100%
53L-108-5.2Cable Trenching for Counterpoise WireLF2,5051.253,131.252,505.003,131.25100%
54L-108-5.3No. 6 Bare Counterpoise WireLF2,6351.654,347.752,635.004,347.75100%
55L-108-5.424-strand Multimode Fiber Optic CableLF80030.0024,000.00800.0024,000.00100%
56L-108-5.61/C No. 8, 5kV Type C CableLF2,6952.506,737.502,695.006,737.50100%
57L-110-5.11-1/2 inch Dia. PVC Conduit, Type 1LF2,6053.509,117.502,605.009,117.50100%
58L-125-2.7Removal and Re-Installation of Existing L-861T Taxiway Edge LightEA41,550.006,200.005.007,750.00125%Insufficient clearance from work limits to an additional light for it to remaining in-place without likelihood of damage.
59L-125Temporary Taxiway C Electrical ServiceLS19,750.009,750.001.009,750.00100%
TOTAL7,784,492.25SUB-TOTAL8,075,611.90
Reconciling Change Order 2 New Items
CO2-1Remove and dispose of: 112 feet 18-inch RCP; 140 feet 42-inch RCP; one structureLS120,786.00The specific pipe segments and structure were encountered during excavation and were not apparent on as-built plans or feel surveys. The 18 inch pipe was in very poor condition but part of a functioning system and required replacement. Refer item CO2-2
CO2-2Provide and install 128 feet 18-inch RCPLS111,283.00Refer item CO2-1
CO2-3Provide and install fiber-optic junction boxesLS15,071.00Airport request to extend fiber-optic junction box to the ground surface for ease of future access
CO2-4Provide and install temporary runway distance to go signsLS15,981.00Airport operational safety request to provide pilots active information to supplement NOTAM furnished data.
CO2-5Temporarily cover runway/taxiway signs.LS14,010.00Airport operational safety request to improve night operations
CO2-6Provide and install safety orange fencingLS15,676.00Airport operational safety request to improve day operations
CO2-7Remove and replace 4 sections of concrete duct bankLS120,962.00Required to help resolve unexpected utility conflicts
CO2-8Plug existing 48-inch RCPLS11,430.00Required to maintain correct flow paths due to pipe connection not shown on as-builts or field survey, but exposed during excavation work.

Page 2 of 3