FINAL RECONCILING CHANGE ORDER - CHANGE ORDER NO. 2 Sarasota Bradenton International Airport Master Drainage System Improvements Quality Enterprises USA, Inc. Dates: From 10/17/2019 To: 10/29/2021

ItemSpecificationDescriptionUnitQuantityUnit CostAmountFinal QuantityAmountPercentComment
1C-100Contractor Quality Control ProgramLS1$ 63,000.00$ 63,000.001$ 63,000.00100%
2C-102-5.1aSynthetic BalesLF3,725$ 2.25$ 8,381.253,865$ 8,696.25104%Additional erosion and sedimentation controls needed to comply with discharge water quality 29 NTU limits. As a permit condition this item is performance-based and can vary with rainfall, soil erodibility, and other factors that cannot be fully defined in advance
3C-102-5.1eInstallation and Removal of Silt FenceLF7,680$ 1.00$ 7,680.009,280$ 9,280.00121%Refer item 2
4C-102-5.1fCheck DamsEA7$ 250.00$ 1,750.0015$ 3,750.00214%Refer item 2
5C-102-5.1gInlet ProtectionEA7$ 120.00$ 840.0036$ 4,320.00514%Refer item 2 and 40. Also note some areas required double and triple normal inlet protection
6C-102-5.1hFloating Turbidity BarriersLF1,520$ 6.00$ 9,120.001,450$ 8,700.0095%Normal variance
7C-102-5.1iSoil Tracking Prevention DeviceEA7$ 2,000.00$ 14,000.0014$ 28,000.00200%Additional access locations required additional small tracking prevention devices
8C-105MobilizationLS1$ 545,000.00$ 545,000.001$ 545,000.00100%
9P-101-5.1Pavement RemovalSY7,748$ 5.25$ 40,677.006,325$ 33,206.2582%The contractor opted to use a trench box which reduced cuts in the existing pavement compared to laid-back slopes provided for in the original bid.
10P-101-5.2Removal of Pipe and Other Buried StructuresLS1$ 30,000.00$ 30,000.001$ 30,000.00100%
10aP-101-5.2Removal of Pipe and Other Buried Structures(Twy C)LS1$ 76,180.00$ 76,180.001$ 76,180.00100%
11P-151-4.1ClearingAC44.0$ 625.00$ 27,500.0044$ 27,500.00100%
12P-151-4.2Clearing and GrubbingAC16.0$ 2,100.00$ 33,600.0016$ 33,600.00100%
13P-152-4.1Embankment in PlaceCY113,810$ 10.40$ 1,183,624.00130,904$ 1,361,401.60115%Two ponds in phase 4 and one pond in phase 3 had scour depths greater and more extensive than revealed by the initial hydrographic survey. The marshy area in phase 1 had root mats extending 12 inches deeper than originally estimated. The area was not accessible for geotechnical exploration at the time of the original design.
14P-154-5.1Subbase CourseSY10,215$ 8.00$ 81,720.009,140.00$ 73,120.0089%The contractor opted to use a trench box which reduced cuts in the existing pavement compared to laid-back slopes provided for in the original bid. This reduced the subbase quantity needed.
17P-219-6.1aRecycled Concrete Aggregate Base Course (9-inch)SY6,390$ 19.00$ 121,410.006,808.00$ 129,352.00107%Connection to existing pavement required additional base at the transition. Also refer item 20a
18P-219-6.1bRecycled Concrete Aggregate Base Course (14-inch)SY3,825$ 26.00$ 99,450.002,075.00$ 53,950.0054%The contractor opted to use a trench box which reduced cuts in the existing pavement compared to laid-back slopes provided for in the original bid. This reduced the base quantity needed.
19P-401-8.1Asphalt Surface CourseTON990$ 170.00$ 168,300.00606.50$ 103,105.0061%The contractor opted to use a trench box which reduced cuts in the existing pavement compared to laid-back slopes provided for in the original bid. This reduced the surface quantity needed.
20P-403-8.1Asphalt Mixture Surface CourseTON1,100$ 170.00$ 187,000.001,138.30$ 193,511.00103%Normal variance
20aFDOT Sec 334Asphalt SP 12.5 Surface CourseTON25$ 170.00$ 4,250.0026.49$ 4,503.30106%Normal variance
21P-602-5.1Emulsified Asphalt Prime CoatGAL2,273$ 9.00$ 20,457.000.00$ -0%Prime coat was not needed due to weather and construction conditions
22P-603-5.1Emulsified Asphalt Tack CoatGAL267$ 8.00$ 2,136.00283.50$ 2,268.00106%Normal variance
23P-620-5.1aSurface PreparationLS1$ 7,250.00$ 7,250.001.00$ 7,250.00100%
24P-620-5.1bMarkingSF3,200$ 6.00$ 19,200.002,853.00$ 17,118.0089%Trench box use required less remarking of airfield pavement due to narrower cuts and required reconstruction
25P-620-5.1cReflective MediaLB92$ 18.00$ 1,656.00230.00$ 4,140.00250%Additional reflective media were required for consistency with adjacent markings and improved visibility
26P-620-5.1dTemporary Runway and Taxiway MarkingSF1,100$ 5.00$ 5,500.001,210.00$ 6,050.00110%Adjusted based on field observations and operating requirements
27P-621-5.1GroovingSY1,650$ 3.50$ 5,775.001,650.00$ 5,775.00100%
28F-162-5.1Chain Link FenceLF100$ 40.00$ 4,000.000.00$ -0%Not required for secure access
29F-162-5.2Vehicle GateEA1$ 2,500.00$ 2,500.000.00$ -0%Not required for secure access
30D-701-5.1a24-inch RCP, Class V, Complete in-placeLF1,288$ 93.50$ 120,428.00112.00$ 10,472.009%Existing pipes beneath the water surface were of different sizes and configurations than indicated by survey or as-built plans. This required resisting to maintain the system hydraulics consistent with planned future expansions. Refer also to items 31 and 40.
31D-701-5.1b30-inch RCP, Class V, Complete in-placeLF1,656$ 125.00$ 207,000.003,152.00$ 394,000.00190%Refer to item 30 above

Page 1 of 3