November 22, 2021 Board Meeting - Items Needing Action - Over $325,000 Threshold
SARASOTA BRADENTON INTERNATIONAL AIRPORT SARASOTA MANATEE AIRPORT AUTHORITY 6000 AIRPORT CIRCLE SARASOTA, FLORIDA 34243
CHANGE ORDER
Project Title: Master Drainage Improvements Date Prepared: FAA AIP No. 3-12-0071-057-2019
Project Description: Improvements to Master Drainage System to enhance water quality management and flood protection. FDOT Fin. Proj. No. G.L. Acct. No. 18027-00-000
Contractor: Quality Enterprises USA, Inc. Change Order # 02 Final Reconciling
Address: 3494 Shearwater Street Naples, FL 34117
ORIGINAL CONTRACT AMOUNT: $ 7,359,282.00
COST OF PREVIOUS CHANGE ORDERS: $ 425,252.75
COST OF THIS CHANGE ORDER: $ 504,224.15
REVISED CONTRACT AMOUNT: $ 8,288,758.90
DESCRIPTION OF CHANGE QUANTITY UNIT PRICE TOTAL AMOUNT
Final Reconciling Change Order - See attached quantity and cost sheets
Reason for Change Order:
Reconciling As-Built quantities and costs. See attached quantity and cost sheets for individual item comments
Subject to the conditions set forth below, an equitable adjustment is established as follows:
The contract price is ... The contract time to complete work is ...
✓ Not changed. Not changed.
The foregoing is in accordance with your contract dated October 17, 2019 and as listed below: A. The aforementioned change and work affected thereby are subject to all contract stipulations and covenants. B. The rights of the Owner are not prejudiced; and C. All claims against the Owner which are incidental to or as a consequence of the aforementioned change are satisfied. Increased $504,224.15 ✓ Increased - Completion Date October 29, 2021
SIGNATURE
Owner Representative: Sarasota Manatee Airport Authority TITLE DATE
Contractor: Quality Enterprises USA, Inc. Chairman, SMAA
Engineer of Record: EG Solutions, Inc.
FDOT (if applicable)
DISTRIBUTION: Copy for Each Signatory Party, SMAA Finance, SMAA Project File
FAA: (if applicable)