Construction Documents: The main objective of the Construction Document Phase will be to prepare documents which include sufficient detail required to construct the project.

  1. Building Envelope Review (CMC): Envelope/Water Intrusion Consultant (CMC) to perform the following building envelope review services/tasks for each of the following project components during the 60% and 90% construction document phases with deliverables in the form of narrative (PDF) commentary for applicable technical specifications and "redline" comments on the drawings: Ground Boarding Facility (GBF), Concourse B Expansion (Bump-outs), Main terminal Hub—escalator work (pit waterproofing).
  2. One (1) review of interim (60%) CD documents for each of the above project components.
  3. Include summary of review comments and recommendations to guide workshop activity.
  4. One (1) 1-day workshop with AOR to review comments and recommendations as well as additional design concerns/considerations.
  5. One (1) review of final CD documents for each of the above project components
  6. Include summary of review comments and recommendations for follow-up meeting.
  7. One (1) follow-up meeting/work-session with AOR to discuss final comments and recommendations.
  8. Task 2 60% Construction Document Deliverables include (to Gresham Smith only):
  9. Electronic (PDF) "redline" markups on drawings for workshop
  10. Narrative commentary of applicable specification sections for workshop
  11. Task 2 90% Construction Document Deliverables include:
  12. Electronic (PDF) "redline" markups on drawings
  13. Narrative commentary of applicable specification sections
  14. Task 3 60% Construction Document Deliverables include (to MLM Martin only):
  15. Electronic (PDF) "redline" markups on drawings for workshop
  16. Narrative commentary of applicable specification sections for workshop
  17. Task 3 90% Construction Document Deliverables include:
  18. Electronic (PDF) "redline" markups on drawings
  19. Narrative commentary of applicable specification sections
  20. Bidding and GMP Support Services: Coordinate with the CM and respond to questions and requests for information arising from bidding the project:
  21. Provide supplemental drawings, respond to RFI's, issue addenda.
  22. Assist the CM with sub-contractor meetings
  23. Assist in price evaluation meetings

Excluded Requirements

  • All Construction Administration is excluded from this agreement and will be determined and added later in conjunction with the approved construction schedule and phasing plan.
  • Any hazardous materials surveying is excluded from this agreement.

End Scope of Services

Page | 48