Construction Documents: The main objective of the Construction Document Phase will be to prepare documents which include sufficient detail required to construct the project.
- Building Envelope Review (CMC): Envelope/Water Intrusion Consultant (CMC) to perform the following building envelope review services/tasks for each of the following project components during the 60% and 90% construction document phases with deliverables in the form of narrative (PDF) commentary for applicable technical specifications and "redline" comments on the drawings: Ground Boarding Facility (GBF), Concourse B Expansion (Bump-outs), Main terminal Hub—escalator work (pit waterproofing).
- a.One (1) review of interim (60%) CD documents for each of the above project components.
- i.Include summary of review comments and recommendations to guide workshop activity.
- b.One (1) 1-day workshop with AOR to review comments and recommendations as well as additional design concerns/considerations.
- c.One (1) review of final CD documents for each of the above project components
- i.Include summary of review comments and recommendations for follow-up meeting.
- d.One (1) follow-up meeting/work-session with AOR to discuss final comments and recommendations.
- Task 2 60% Construction Document Deliverables include (to Gresham Smith only):
- a.Electronic (PDF) "redline" markups on drawings for workshop
- b.Narrative commentary of applicable specification sections for workshop
- Task 2 90% Construction Document Deliverables include:
- a.Electronic (PDF) "redline" markups on drawings
- b.Narrative commentary of applicable specification sections
- Task 3 60% Construction Document Deliverables include (to MLM Martin only):
- a.Electronic (PDF) "redline" markups on drawings for workshop
- b.Narrative commentary of applicable specification sections for workshop
- Task 3 90% Construction Document Deliverables include:
- a.Electronic (PDF) "redline" markups on drawings
- b.Narrative commentary of applicable specification sections
- Bidding and GMP Support Services: Coordinate with the CM and respond to questions and requests for information arising from bidding the project:
- a.Provide supplemental drawings, respond to RFI's, issue addenda.
- b.Assist the CM with sub-contractor meetings
- c.Assist in price evaluation meetings
Excluded Requirements
- a.All Construction Administration is excluded from this agreement and will be determined and added later in conjunction with the approved construction schedule and phasing plan.
- b.Any hazardous materials surveying is excluded from this agreement.
End Scope of Services
Page | 48