PROJECT SCOPE OF SERVICES - Scope Detail (CMC - ENVELOPE)
These Scope Details define the level of service and the processes involved, and describe the characteristics of the deliverables the consultant will produce while engaging in the tasks and Elements of Work listed in the Scope Outline above.
Pre-Design Services – Envelope/Water Intrusion Consultant (CMC) to perform existing conditions survey to review existing building envelope conditions and related considerations for new building envelope penetrations (e.g., wall fenestrations, etc.) and requirements for tie-in junctures between new/renovation and existing construction.
- Existing Envelope Survey (CMC): Envelope/ Water Intrusion Consultant (CMC) will perform the following tasks to complete the survey described above.
- a.Site Visit: One (1) full-day site visit with Gresham Smith to walk the affected existing site conditions, photograph and otherwise document existing conditions and potential existing issues/concerns. Produce site visit report for Gresham Smith and the Authority for review
- b.Site Visit Report Review: Virtual meeting with Gresham Smith and Authority to review site visit report.
- Pre-Design Services Deliverables include:
- a.Electronic (PDF) site visit report.
- Design Development Documents and Early Release Packages (ERP)- The Design Development documents will refine and further develop the design concept and space planning established during the Schematic Design Phase.
- Building Envelope Review (CMC): Envelope/Water Intrusion Consultant (CMC) to perform the following building envelope review services/tasks for each of the following project components at the completion of 100% Design Development with deliverables in the form of narrative commentary (PDF) for applicable technical specifications and "redline" comments on the drawings.: Ground Boarding Facility (GBF), Concourse B Expansion (Bump-outs), Main terminal Hub—escalator work (pit waterproofing).
- a.One (1) review of final DD Documents for each of the above project components.
- i.Include summary of review comments and recommendations to guide workshop activity.
- b.One (1) 1-day workshop to review comments and recommendations as well as additional design concerns/considerations
- Task 2 Design Development Deliverables include (to Gresham Smith only):
- a.Electronic (PDF) "redline" markups on drawings for workshop
- b.Narrative commentary of applicable specification sections for workshop
- Task 3 Design Development Deliverables include (to MLM Martin only):
- a.Electronic (PDF) "redline" markups on drawings for workshop
- b.Narrative commentary of applicable specification sections for workshop