a. Design development shall provide further refinement of Schematic Design documents, to include the following:
Coordination Meetings
Updated load calculations
Prepare long form technical specifications.
Sustainability and Energy Modeling refinement for code compliance
Riser and Flow Diagrams Development
Lighting and Power Development
Fire protection plans showing scope of work, delegated design level.
Phasing Development
Controls Diagrams Development, including coordination with Owner on overall controls schemes.
Additional existing conditions survey work, as required, to support Design Development.
Internal Quality Assurance / Quality Control
60% page turn with SRO, address review comments.
Symbol Legends, Abbreviations, Code Compliance
Floor Plans
Enlarged Floor Plans for Mechanical and Electrical Rooms
One-line diagrams
Details
Schedules
Specifications for Divisions 21, 22, 23, 26
Task 3 Design Development Deliverables include:
Symbol Legends, Abbreviations, Code Compliance
Floor Plans
Enlarged Floor Plans for Mechanical and Electrical Rooms
One-line diagrams
Details
Schedules
Specifications for Divisions 21, 22, 23, 26
Construction Documents: The main objective of the Construction Document Phase will be to prepare documents which include sufficient detail required to construct the project.
MEP&FP Systems (TLC): Perform MEP&FP engineering design services for each project component including the CEP improvements (design is based on Option 1 being selected; if SMAA selects Option 2, additional design will be necessary), Ground Boarding Facility, Concourse B Expansion and Main Terminal Expansion elements. The construction documents will be fully coordinated with respective disciplines within the Revit model in accordance with the BIM execution plan.
Continuation of the Design Development phase of work
Owner/Architect Meetings
Construction Documents shall provide further refinement of Design Development, to include the following:
Page | 35