SCOPE DETAIL
- b.Structural Framing Design
- c.Design Production
- ii.Continue to develop the design to issue ERP documents for permitting and GMP preparation by the CM.
- iv.Finalize the foundation design for the jet blast fence to protect auto parking.
- i.Advance the design of columns, beams, slabs, and lateral resisting elements.
- ii.Coordinate and advance the details
- iii.Further the electronic documents showing the structural framing layout.
- i.Coordinate structural framing with other disciplines.
- ii.Prepare Structural General Notes.
- iii.Create plan drawings for the following:
- Foundations
- Floor and roof framing plans
- Prepare column and wall schedules.
- Provide elevations of Lateral resisting elements.
- Advance the detailing of structural conditions.
- Generate building sections and elevations as appropriate.
- Prepare long form technical specifications.
- Task 2 Design Development Deliverables include:
- a.Develop and complete foundation drawings and calculations, including blast fence foundation plans.
- b.Develop drawings and documents for the framing design.
- c.Develop drawings for building foundations, columns, walls, structural elevations, details and sections.
- d.Develop preliminary technical specifications, reports, calculations and required documentation for the structural work component.
- .
- Construction Documents: The main objective of the Construction Document Phase will be to prepare documents which include sufficient detail required to construct the project.
- Civil Site Design (AECOM): Construction Contract Administration scope for the ERP package will be submitted separately and not included as part of this scope.
- a.Utilities – incorporate all comments received from permitting agencies and the design team/CM and finalize the designs. Respond to permitting comments.
- b.Apron – incorporate all comments received from the design team/CM and finalize design.
- c.Shade Parking Lot – incorporate all comments received from the design team/CM and finalize design.
- d.Construction Safety and Phasing Plan and 7460-1 Notice of Proposed Construction – respond to comments received from FAA and resubmit as required.
- Task 2 Construction Document Deliverables include:
- a.Finalize all utility drawings and plans. Respond to any permitting comments that have not been incorporated.
- b.Finalize all apron drawings and plans. Finalize erosion control and apron utility plans and drawings.
- c.Finalize all shade parking plans and drawings. Finalize marking plans and road wayfinding signage.
- d.Incorporate or incorporate any FAA comments to the CSPP or phasing plan and re-submit if required.
- e.Finalize technical specifications, reports, calculations and required documentation for the civil work component.