November 22, 2021 Board Meeting - Items Needing Action - Over $325,000 Threshold
SCOPE DETAIL
Structural Framing Design
Design Production
Scope of Services November 9, 2021
Continue to develop the design to issue ERP documents for permitting and GMP preparation by the CM.
Finalize the foundation design for the jet blast fence to protect auto parking.
Advance the design of columns, beams, slabs, and lateral resisting elements.
Coordinate and advance the details
Further the electronic documents showing the structural framing layout.
Coordinate structural framing with other disciplines.
Prepare Structural General Notes.
Create plan drawings for the following:
Foundations
Floor and roof framing plans
Prepare column and wall schedules.
Provide elevations of Lateral resisting elements.
Advance the detailing of structural conditions.
Generate building sections and elevations as appropriate.
Prepare long form technical specifications.
Task 2 Design Development Deliverables include:
Develop and complete foundation drawings and calculations, including blast fence foundation plans.
Develop drawings and documents for the framing design.
Develop drawings for building foundations, columns, walls, structural elevations, details and sections.
Develop preliminary technical specifications, reports, calculations and required documentation for the structural work component.
.
Construction Documents: The main objective of the Construction Document Phase will be to prepare documents which include sufficient detail required to construct the project.
Civil Site Design (AECOM): Construction Contract Administration scope for the ERP package will be submitted separately and not included as part of this scope.
Utilities – incorporate all comments received from permitting agencies and the design team/CM and finalize the designs. Respond to permitting comments.
Apron – incorporate all comments received from the design team/CM and finalize design.
Shade Parking Lot – incorporate all comments received from the design team/CM and finalize design.
Construction Safety and Phasing Plan and 7460-1 Notice of Proposed Construction – respond to comments received from FAA and resubmit as required.
Task 2 Construction Document Deliverables include:
Finalize all utility drawings and plans. Respond to any permitting comments that have not been incorporated.
Finalize all apron drawings and plans. Finalize erosion control and apron utility plans and drawings.
Finalize all shade parking plans and drawings. Finalize marking plans and road wayfinding signage.
Incorporate or incorporate any FAA comments to the CSPP or phasing plan and re-submit if required.
Finalize technical specifications, reports, calculations and required documentation for the civil work component.
Page | 25