MAIN CHECKPOINT FLOOR PLAN - FINAL SCALE: $ 3/32" = 1' - 0" $

  • CONTRACTOR SHALL COORDINATE DELIVERY PATH, FLOOR PROTECTION, AND DELIVERY TIMES WITH THE AIRPORT. CONTRACTOR SHALL COORDINATE WITH DESIGNER/STRUCTURAL ENGINEER TO EVALUATE THE STRUCTURAL INTEGRITY OF THE DELIVERY PATH AND FINAL POSITION. RETURNED TO OWNER.
  • EQUIPMENT REFERENCE POINT
  • RE: 1/APD101 FOR EXISTING EQUIPMENT.
  • THE DESIGN IS BASED ON THE CHECKPOINT REQUIREMENTS AND PLANNING GUIDE (CRPG) REVISION 0 DATED 12/17/2018.

GENERAL NOTES

  1. UTILIZE EXISTING STANCHIONS TO PROVIDE THE CONFIGURATION SHOWN. PROJECT SPONSOR TO SUPPLY ADDITIONAL STANCHIONS WHERE NECESSARY.
  2. PROVIDE NEW EQUIPMENT. RE: ARN101.
  3. RELOCATED EQUIPMENT. RE: ARN101.

NOTES BY SYMBOL "○"

SMITHS 6040ATIX AT2 INCLUDES ONE INFEED ROLLER, ONE SCANNER UNIT, ONE HSC, AND ONE 6'-8" EXIT ROLLER. SARASOTA BRADENTON INTERNATIONAL

  • LOCAL TSA AND PROJECT SPONSOR SHALL DETERMINE THE AVAILABILITY OF ALL NEW EQUIPMENT PRIOR TO THE WORK (RE: ARN101), INCLUDING BUT NOT LIMITED TO THE FOLLOWING:
  • ETD-8LS COMBINATION MOBILE CABINET
  • EXTENSION ROLLERS
  • TDC PODIUMS
  • ADA GATES & BARRIERS
  • COMPOSURE BENCHES WHERE "AVAILABLE": LOCAL TSA SHOW PROCURE VIA THE REMAG PROCESS AND INSTALL CONTRACTOR IS NOT RESPONSIBLE FOR PROCUREMENT. WHERE "UNAVAILABLE": PROJECT SPONSOR SHALL PROCUREMENT FROM VENDOR AND INSTALL CONTRACTOR WILL UTILIZE EXISTING EQUIPMENT DURING INTERIM PERIOD WHILE NEW EQUIPMENT SHIPS FROM VENDOR. srq

K2 CONSTRUCTION CONSULTANTS, INC. 4330 East-West Highway, Suite 320, Bethesda, MD 20814 301.656.2228 | servicerequest@k2consulting.com www.k2consulting.com