C301 – Geometry Plan:
1. Added curb skirts at the long-term parking spaces.
C302 – Geometry Plan:
1. Removed two ADA ramps at the west end of the existing long-term lot (sidewalk).
C401A – Grading and Drainage Plan:
1. Modified typical shelter section A-A
Specifications:
- FDOT 327 Milling of existing asphalt
- FDOT 948 Optional drainage products.
Schedule of Quantities - Existing Items
ItemC-9 Clearing and grubbing: $1,850.00
Increased from 2.6 ACRE to 2.8 ACRE.
Item C-12 Demolish trees:
Increased from 63 EA to 77 EA.
Item C-16 Demolish curb: $1,100.00 Increased from 4400 LF to 4510 LF.
- Item C-21 Demolish Asphalt Pavement and base course: $2,250.00 Increased from 7,300 SY to 7,425 SY.
- Item C-24 12" Type B stabilization LBR 40: $ 950.00 Increased from 15,000 SY to 15,055 SY.
- Item C-25 FDOT optional base group 4: $1,235.00 Increased from 14,000 SY to 14,055 SY.
- Item C-26 Superpave Asphaltic concrete: $3,000.00
Increased from 19,000 TON to 19,015 TON.
- Item C-27 Concrete curb, Type D: $1,020.00
Increased from 2500 LF to 2840 LF. curb prep
- Item C-29 Concrete Sidewalk and Driveways:
Added 68 SY for curb skirts
Skirt grading, compacting and clean up after poured
Deleted 18 SY for two ADA sidewalk ramps
$3,750.00
Schedule of Quantities - New Items
Item C-46 Adjust/ Raise/ Modify Manhole:
1 EA.
$1,430.00
Item C-47 1" Asphalt milling:
24 SY $1,250.00