C301 – Geometry Plan: 1. Added curb skirts at the long-term parking spaces.

C302 – Geometry Plan: 1. Removed two ADA ramps at the west end of the existing long-term lot (sidewalk).

C401A – Grading and Drainage Plan: 1. Modified typical shelter section A-A

Specifications:

  • FDOT 327 Milling of existing asphalt
  • FDOT 948 Optional drainage products.

Schedule of Quantities - Existing Items

ItemC-9 Clearing and grubbing: $1,850.00 Increased from 2.6 ACRE to 2.8 ACRE.

Item C-12 Demolish trees: Increased from 63 EA to 77 EA.

Item C-16 Demolish curb: $1,100.00 Increased from 4400 LF to 4510 LF.

  • Item C-21 Demolish Asphalt Pavement and base course: $2,250.00 Increased from 7,300 SY to 7,425 SY.
  • Item C-24 12" Type B stabilization LBR 40: $ 950.00 Increased from 15,000 SY to 15,055 SY.
  • Item C-25 FDOT optional base group 4: $1,235.00 Increased from 14,000 SY to 14,055 SY.
  • Item C-26 Superpave Asphaltic concrete: $3,000.00 Increased from 19,000 TON to 19,015 TON.
  • Item C-27 Concrete curb, Type D: $1,020.00 Increased from 2500 LF to 2840 LF. curb prep
  • Item C-29 Concrete Sidewalk and Driveways: Added 68 SY for curb skirts Skirt grading, compacting and clean up after poured Deleted 18 SY for two ADA sidewalk ramps $3,750.00

Schedule of Quantities - New Items

Item C-46 Adjust/ Raise/ Modify Manhole: 1 EA. $1,430.00

Item C-47 1" Asphalt milling: 24 SY $1,250.00