C301 – Geometry Plan: 1. Added curb skirts at the long-term parking spaces.
C302 – Geometry Plan: 1. Removed two ADA ramps at the west end of the existing long-term lot (sidewalk).
C401A – Grading and Drainage Plan: 1. Modified typical shelter section A-A
Specifications:
FDOT 327 Milling of existing asphalt
FDOT 948 Optional drainage products.
Schedule of Quantities - Existing Items
ItemC-9 Clearing and grubbing: $1,850.00 Increased from 2.6 ACRE to 2.8 ACRE.
Item C-12 Demolish trees: Increased from 63 EA to 77 EA.
Item C-16 Demolish curb: $1,100.00 Increased from 4400 LF to 4510 LF.
Item C-21 Demolish Asphalt Pavement and base course: $2,250.00 Increased from 7,300 SY to 7,425 SY.
Item C-24 12" Type B stabilization LBR 40: $ 950.00 Increased from 15,000 SY to 15,055 SY.
Item C-25 FDOT optional base group 4: $1,235.00 Increased from 14,000 SY to 14,055 SY.
Item C-26 Superpave Asphaltic concrete: $3,000.00 Increased from 19,000 TON to 19,015 TON.
Item C-27 Concrete curb, Type D: $1,020.00 Increased from 2500 LF to 2840 LF. curb prep
Item C-29 Concrete Sidewalk and Driveways: Added 68 SY for curb skirts Skirt grading, compacting and clean up after poured Deleted 18 SY for two ADA sidewalk ramps $3,750.00
Schedule of Quantities - New Items
Item C-46 Adjust/ Raise/ Modify Manhole: 1 EA. $1,430.00
Item C-47 1" Asphalt milling: 24 SY $1,250.00