SARASOTA BRADENTON INTERNATIONAL AIRPORT SARASOTA MANATEE AIRPORT AUTHORITY 6000 AIRPORT CIRCLE SARASOTA, FLORIDA 34243

Project Title: Parking Lot Expansion Phase 2 Project Date Prepared: AIP No. September 20, 2021

Project Description: Expansion of various airport parking areas. FDOT Fin. Proj. No. N/A

G.L. Acct. No. N/A

Contractor: Magnum Builders of Sarasota, Inc. Change Order # 17515-00-000

Address: 4545 Northgate Court Sarasota, FL 34243 07

ORIGINAL CONTRACT AMOUNT: $ 2,027,774.09

COST OF PREVIOUS CHANGE ORDERS: $ 818,266.03

COST OF THIS CHANGE ORDER $ 1,101,171.75

REVISED CONTRACT AMOUNT: $ 3,947,211.87

DESCRIPTION OF CHANGE QUANTITY UNIT PRICE TOTAL AMOUNT

  • ADD Scope to expand Ready/Return Lot, add covered walkway per attached detail:
  • 15' x 432' Tensile Membrane Canopy 1 LS 699,090.00 $699,090.00
  • Survey Work 1 LS 4,000.00 $4,000.00
  • Demo Existing bays of parking canopy 1 LS 15,000.00 $15,000.00
  • Canopy Site Work 1 LS 33,810.00 $33,810.00
  • Canopy Electrical 1 LS 85,310.00 $85,310.00
  • Demo Sidewalk 1 LS 10,560.00 $10,560.00
  • Concrete Foundations 1 LS 53,762.00 $53,762.00
  • 4" thick Concrete Sidewalk 1 LS 28,160.00 $28,160.00
  • Temporary Fence 1 LS 8,050.00 $8,050.00
  • Temporary Toilets 1 LS 380.00 $380.00
  • Project Manager 1 LS 21,600.00 $21,600.00
  • Superintendent 1 LS 48,000.00 $48,000.00
  • Project Coordinator 1 LS 3,600.00 $3,600.00
  • Dumpster 1 LS 1,000.00 $1,000.00
  • Survey/Layout for As-Built 1 LS 6,050.00 $6,050.00
  • Subtotal: $1,018,372.00

GL Insurance: $10,183.72

CM Fee: $61,713.34

Subtotal: $1,090,269.06

Performance & Payment Bond: $10,902.69

Change Order Total: $1,101,171.75

Reason for Change Order: Changes due to owner requested additions.

Subject to the conditions set forth below, an equitable adjustment is established as follows:

The contract price is ... The contract time to complete work is ...

not changed. not changed.

X Increased X Increased 210-days

The foregoing is in accordance with your contract dated A. The aforementioned change and work affected thereby are subject to all contract stipulations and covenants. B. The rights of the Owner are not prejudiced; and C. All claims against the Owner which are incidental to or as a consequence of the aforementioned change are satisfied. April 10,2020 and as listed below:

SIGNATURE TITLE DATE

Owner Representative: Chairman, SMAA