Project Title: Parking Lot Expansion Phase 2 Project Date Prepared: AIP No. September 20, 2021
Project Description: Expansion of various airport parking areas. FDOT Fin. Proj. No. N/A
N/A
Contractor: Magnum Builders of Sarasota, Inc. G.L. Acct. No. 17515-00-000
Address: 4545 Northgate Court Change Order # 06
Sarasota, FL 34243
ORIGINAL CONTRACT AMOUNT: $ 2,027,774.09
COST OF PREVIOUS CHANGE ORDERS: 545,855.03
COST OF THIS CHANGE ORDER 272,411.00
REVISED CONTRACT AMOUNT: $ 2,846,040.12
DESCRIPTION OF CHANGE QUANTITY UNIT PRICE TOTAL AMOUNT
ADD Scope to construct airline tenant buildout per attached detail:
General Conditions 1 LS 33,260.00 $33,260.00
Site work 1 LS 11,490.00 $11,490.00
Masonry 1 LS 1,500.00 $1,500.00
Wood & Plastic 1 LS 14,097.00 $14,097.00
Doors/frames/window/ hardware 1 LS 14,545.00 $14,545.00
Finishes 1 LS 41,812.00 $41,812.00
Specialties 1 LS 821.00 $821.00
Equipment 1 LS 6,809.00 $6,809.00
Mechanical/HVAC/Plumbing 1 LS 81,849.00 $81,849.00
Electrical 1 LS 42,589.00 $42,589.00
Subtotal: $248,772.00
GL Insurance: $2,588
CM Fee: $17,821.00
Subtotal: $269,181.00
Performance & Payment Bond: $3,230.00
Change Order Total: $272,411.00
Reason for Change Order: Changes due to owner requested additions.
Subject to the conditions set forth below, an equitable adjustment is established as follows:
The contract price is ... The contract time to complete work is ...
not changed. not changed.
X Increased X Increased 30-days
The foregoing is in accordance with your contract dated A. The aforementioned change and work affected thereby are subject to all contract stipulations and covenants. B. The rights of the Owner are not prejudiced; and C. All claims against the Owner which are incidental to or as a consequence of the aforementioned change are satisfied. April 10,2020 and as listed below:
SIGNATURE TITLE DATE
Owner Representative: Chairman, SMAA
Contractor Magnum Builders
Design Consultant AID, Inc.
FAA: (if applicable) N/A
FDOT (if applicable) N/A