Project Fee Proposal - TLC Engineering Solutions
Sunsolia Brudenton Airport
Rental Car Facility Quick Turn Around and Maintenance Area - Add Service No. 1 - Garage
7/3/2021
Design Phases Director Project Manager Sr. Mech Eng Mech Eng II Mech Eng I FP Eng Plumbing Eng Sr. Elect Eng Elect Eng II Elect Eng I Sr. Technology Tech Designer Administrative Total
Task Description
1 Task 1 - Programming (20%)
2 Coordination of team activities, scheduling, and project commi 8 2 2 4 4 2 4 26
3 Utility and infrastructure review and recommendations 4 4 4 12
4 Basis of Design Document 2 2 2 2 8
5 Project Management 2 8 10
Task 1 - Subtotal Hours 2.00 16.00 - - - - 2.00 2.00 10.00 4.00 2.00 8.00 10.00 - 56
Subtotal Direct Labor $420.38 $1,777.44 -- -247.12 $203.92 $1,985.90 $494.24 $203.92 $1,636.00 $982.90 -9,351.82
7 Task 2 - Schematic Design (40%) (8 weeks)
8 Design Meetings (x6) 4 4 4 12
9 OAC Meetings (x2) 2 2 2 6
10 Code analysis 6 2 2 10
11 Calculations 4 4 2 4 14
12 Design Concepts Validation - Narrative 0
13 SMAA Page flip 4 4 2 2 12
14 Coordination 4 8 2 4 2 4 24
15 Quality Control 2 2 2 2 2 10
16 Response to teams QA/QC Comments 2 2 2 2 8
17 Project Management 2 2 4
18 0
Task 2 - Subtotal Hours 2.00 10.00 - - - - 22.00 20.00 18.00 8.00 - 16.00 4.00 - 100
Subtotal Direct Labor $420.38 $1,985.90 -- -2,718.32 $2,039.20 $3,574.62 $988.48 $- $3,272.00 $393.15 -15,392.06
19 Task 3 - Design Development (60%) (12 weeks)
20 Weekly Design Meetings 4 4 4 4 4 4 4 28
21 Weekly OAC Meetings 0
22 Coordination 2 2 2 2 2 2 14
23 Drawing Development 8 8 4 8 4 8 48
24 Specification Development 0
25 SMAA Page flip 4 2 2 2 2 12
26 Quality Control 2 2 2 2 2 2 2 16
27 Response to teams QA/QC Comments 2 2 4 2 4 12
28 Project Management 2 8 10
29 Cell Phone Lot 0
Task 3 - Subtotal Hours 2.00 18.00 - - - - 20.00 20.00 14.00 20.00 12.00 14.00 20.00 - 140
Subtotal Direct Labor $420.38 $3,574.62 -- -2,471.20 $2,039.20 $2,780.26 $2,471.20 $1,223.52 $2,863.00 $1,965.80 -19,809.18
31 Task 4 - Construction Documents (90%) (8 weeks)
32 Weekly Design Meetings 4 4 4 4 4 4 24
33 Weekly OAC Meetings 0
34 Coordination 2 2 2 2 2 2 14
35 Drawing Development 8 8 4 8 8 4 8 48
36 Specification Development 2 2 4 4 48
37 Energy Model 4 16
38 SMAA Page flip 4 2 8 14
39 Quality Control 2 2 2 2 2 2 18
40 Response to Comments 2 2 4 4 2 12
41 Project Management 2 4 6
Task 4 - Subtotal Hours 2.00 14.00 - - - - 22.00 16.00 16.00 20.00 12.00 24.00 20.00 6.00 152
Subtotal Direct Labor $420.38 $2,780.26 -- -2,718.32 $1,631.36 $3,177.44 $2,471.20 $1,223.52 $4,908.00 $1,965.80 $516.66 $21,812.94
43 Task 5 - Bid and Permit Documents (100%) (6 weeks)
44 Bid RFTs 2 2 2 2 2 4 14
45 Plan Review submission 4 4 4 4 4 20
46 Response to Comments 2 2 2 2 2 2 2 14
47 0
Task 5 - Subtotal Hours - 4.00 - - - - 8.00 8.00 8.00 6.00 - 4.00 4.00 6.00 48
Subtotal Direct Labor -794.36 -- -988.48 $815.68 $1,588.72 $741.36 $- $818.00 $393.16 $516.66 $6,656.42
48 Task 6 - Construction Administration 0
49 Submittal Review 0
50 Field Observation 0
51 Response to Questions/Coordination 0
52 Meetings/Management 0
53 Review Change Order Proposals 0
54 Issue Modifications to Documents 0
55 Purchlist/Witness Testing 0
56 Record Drawings 0
57 Project Management 0
Task 6 - Subtotal Hours - - - - - - - - - - - - - - 0
Subtotal Direct Labor -- -- -- -- -- -- -- $-
Subtotal Hours 8.00 62.00 - - - 74.00 66.00 66.00 58.00 26.00 66.00 58.00 12.00 0
Billing Rate $210.19 $198.59 $198.59 $123.56 $101.96 $123.56 $101.96 $198.59 $123.56 $101.96 $204.50 $98.29 $86.11
Subtotal Direct Labor $1,681.52 $12,312.58 -- -9,143.44 $6,729.36 $13,106.94 $7,166.48 $2,650.96 $13,497.00 $5,700.82 $1,033.32 $73,022.42
TOTAL FEE $ 73,022.42