APPENDIX "A"

Sarasota Bradenton International Airport

ConRAC - QTA

PGAL

Phase 1

Schematic / Design Development

Task No. Task Description Principal Sr. Struc. Eng. Struc. Eng. Sr. CAD /BIM CAD /BIM Accounting Admin Total

Hours Hours Hours Hours Hours Hours Hours

1.01 Kick off meeting 4 8 4 4 20

1.02 Design data compilation 2 4 8 14

1.03 Prepare narrative 2 8 0

1.04 Structural systems 4 16 0 20

1.05 Preliminary framing 4 8 8 32 32 84

1.06 Preliminary foundations 8 16 32 16 16 88

1.07 0

1.08 0

Subtotal Hours 24 52 56 48 48 4 4

Direct Labor (Raw Billing Rate) $196.82 $119.51 $87.03 $79.85 $58.91 $80.76 $74.44

Subtotal Direct Labor $4,723.68 $6,214.52 $4,873.68 $3,832.80 $2,827.68 $323.04 $297.76 $23,093.16

Phase 2

Phase 2

Construction Documents

Task No. Task Description Principal Sr. Struc. Eng. Struc. Eng. Sr. CAD /BIM CAD /BIM Accounting Admin Total

Hours Hours Hours Hours Hours Hours Hours

2.01 Meetings / coordination 12 32 24 8 8 4 4 92

2.02 Foundation system design 4 12 40 32 48 136

2.03 Structural framing delegated review 4 12 32 8 56

2.04 Documents production 8 32 80 100 168 388

2.05 Specifications 4 8 4 16

2.06 Prepare deliverable documents 2 4 16 24 48 94

2.07 QA/QC of deliverables 4 16 32 24 76

2.08 0

Subtotal Hours 38 116 224 196 272 4 8

Direct Labor (Raw Billing Rate) $196.82 $119.51 $87.03 $79.85 $58.91 $80.76 $74.44

Subtotal Direct Labor $7,479.16 $13,863.16 $19,494.72 $15,650.60 $16,023.52 $323.04 $595.52 $73,429.72

Total Direct Labor $12,202.84 $20,077.68 $24,368.40 $19,483.40 $18,851.20 $646.08 $893.28 $96,522.88

Structural Engineering | Threshold Inspections | Forensic Engineering