Exhibit C2 - Fee Proposal - Team Synopsis - GARAGE ADDITION
9/13/2021
Firms and Disciplines Project Phases Other Services Subtotals
10% Design 30% SD 60% DD 95% CD 100% CD Bid/Permit CA
PGAL
Project Management - 5,550 $ 7,400 $ 3,700 $ 1,850 na $ 18,500 4.80%
Rental Car Planning - 4,890 $ 6,520 $ 3,260 $ 1,630 na $ 16,300 4.23%
Architecture and Interiors - 47,610 $ 63,480 $ 31,740 $ 15,870 na $ 158,700 41.16%
Masters Consulting Engineers (see attached breakdown of fees)
Structural Engineering - 23,093 $ 44,058 $ 22,029 $ 7,343 na $ 96,523 25.04%
Stantec
Fueling and Systems Engineering - - - - - na - 0.00%
Atkins North America
Civil Engineering - - - - - na - 0.00%
Site Topographic SUE and Survey na - - 0.00%
Landscape Architecture - - - - - na - 0.00%
ESA - Phases 1 and 2 ( to be provided as needed as a contract amendment) $ - 0.00%
TLC Engineering Solutions (see attached breakdown of fees)
M / E / P / FP / IT $ 9,352 $ 15,392 $ 19,809 $ 21,813 $ 6,656 na $ 73,022 18.94%
Tierra
Asbestos Demolition Survey and Screening (to be completed by separate contractor, per discussions with SMAA) $ - 0.00%
Geotechnical Engineering - difference between original scope/fee ($29,562) and new fully defined scope, previously approved $ - 0.00%
Jensen Hughes
Code Report for Garage Addition (ROM, NTE amount) $ 22,500 5.84%
Reimbursable Expenses
Estimate, based on approximately 3.0% of overall fee $ - 0.00%
Totals $ 9,352 $ 96,535 $ 141,267 $ 82,542 $ 33,349 $ - $ 22,500 385,545 100.00%
Notes:
1 Fee proposal includes full design services as outlined in the detailed scope of work and design deliverables Construction Costs Fee %
$ 15,000,000 2.57%
$ 20,000,000 1.93%
$ 25,000,000 1.54%