Table 15: Planning-Level Construction Cost Estimates and ROW Impacts
| FROM | TO | EXISTING NUMBER OF LANES EACH DIRECTION | PROPOSED NUMBER OF LANES EACH DIRECTION | WIDENING COST PER MILE | LENGTH (MILES) | TOTAL COST | POTENTIAL PARCELS IMPACTED |
|---|
| Touchton Rd | Lake Josephine Dr | 2 | 3 | $ 6,046,201 | 0.59 | $ 3,600,000 | 19 |
|---|
| Lake Josephine Shores Rd | SR 66/US 98 | 2 | 3 | $ 6,046,201 | 2.12 | $ 12,800,000 | 45 |
|---|
| Sebring Pkwy | Lakeview Dr | 3 | 4 | $ 13,025,235 | 1.00 | $ 13,000,000 | 53 |
|---|
| Hammock Rd | Sebring Pkwy | 3 | 4 | $ 13,025,235 | 3.00 | $ 39,100,000 | 140 |
|---|
| Ridge Dr | Highlands/Polk County Line | 3 | 4 | $ 7,283,921 | 1.82 | $ 13,300,000 | 47 |
|---|
CONSTRUCTION COST SUBTOTAL 8.53 $81,800,000 304
Environmental Mitigation $12,500,000
PD&E (8%) $6,500,000
Design (12%) $9,800,000
CEI (12%) $9,800,000
TOTAL ESTIMATED BUILD ALTERNATIVE COST $120,400,000
Note: FDOT Cost per Mile Estimates Used. Rural 4 to 6 lane estimate was modified for the 6 to 8 lane rural scenario as that scenario was not available.
42