8.4 Build Alternative - General – Purpose Lane Widening
Based on the analysis of No-Build Alternative, the capacity deficiencies along the corridor were identified. Capacity deficiencies were noted in the No-Build alternative as measured by LOS values that are not within the acceptable range. Hence general-purpose lane widening/capacity alternative was considered. The major improvements included adding lane capacity to the sections where the LOS was not within the acceptable range in the No-Build Alternative. The proposed improvement sections are shown in Table 8-4. The range of AADTs and peak hour analysis are given in Figure 8-7 and Figure 8-8. The AADT ranges from 17,500 to 71,500. The highest AADTs were observed from Highlands/Polk County Line to south of SR 66 within the study limits.
Table 8-4 – Improvements for sections along US 27
FROMTOImprovements
Touchton RdLake Josephine DrAdding one lane capacity along each direction
Lake Josephine Shores RdSR 66/US 98
Sebring ParkyLakeview Dr
Hammock RdSebring Pkwy
Ridge DrHighlands/Polk County Line
Table 8-5 shows the peak hour volume and LOS for sections along US 27 for General-Purpose Lane Widening/Capacity Alternative.