Florida Department of Transportation REGIONAL APPROACH

US 27 Feasibility Study Results

POPULATION TRENDS

Highlands County is expected to see a 54% increase in population. 12 miles of US 27 have crash rates above the statewide rate.

FREIGHT

US 27 serves a major freight corridor carrying up to 43% truck traffic.

EVACUATION/DETOURS

Limited parallel facilities exist. Potential 67 minute detour to the nearest alternative route. Multiple segments of US 27 have more vehicles (up to 20% more) than can be accommodated.

TRAFFIC CONGESTION

Mobility Analysis

The Mobility Analysis will include a regional traffic, safety, resiliency, and freight evaluations to determine what specific improvements would address existing and future needs. It will also extend into Polk and Glades Counties to assess how enhancements to US 27 will interact with improvements under evaluation by neighboring studies.

Key Components of the Mobility Analysis:

» Operational improvements within limits of the PD&Es

  • Analyzing regional traffic, safety, system resiliency, and freight movement

» Regional project coordination

  • Coordination with ongoing Central Polk Parkway and SR 70 studies

» Consideration for future change in character

  • Addressing the competing roadway demand between people, cars and trucks
  • Alignment with community visions

PD&E Studies

The 2024 Feasibility Study supports a need for two PD&E studies: One from SR 70 to SR 66 and one from SR 66 to US 98.

A PD&E study is an environmental and engineering process which determines social, economic, natural, and physical environmental effects associated with a proposed transportation improvement project. It requires the combined efforts of professional engineers, planners, and scientists who collect and analyze project-related information to develop the best solution for transportation needs. An important component of the process is public and agency coordination.

The following needs are based on the 2024 Feasibility Study findings, and guide the purpose for evaluating improvements.

1. PD&E from SR 70 to SR 66

» Network Resiliency

  • 56-mile detour if an incident occurs on US 27
  • Travel time increases from 20 minutes to an average of 67 minutes with US 27 closure

» Emergency Evacuation

  • Limited North/South roadway alternatives in the region

» Freight Mobility

  • Regional distribution roadway linking Intermodal Logistic Centers
  • Land use changes that continue to drive growth

2. PD&E from SR 66 to US 98

» Land Use Changes

  • Urbanization competes with increased truck traffic
  • New commercial/residential development

» Traffic Congestion

  • Operating at or near capacity by 2045
  • Does not improve with additional lanes

» Safety

  • The fatal crash percentage is more than twice the national average
  • 31% of pedestrian crashes were fatal compared with 8% statewide