{
    "document_id": 15164,
    "page": 139,
    "width_pt": 612,
    "height_pt": 792,
    "rotation": 0,
    "pipeline_version": "paddleocr-vl-1.6+paul-48",
    "engine": "paddleocr_vl",
    "source_run_id": 15275,
    "item_count": 24,
    "counts_by_type": {
        "heading": 3,
        "list": 3,
        "list_item": 15,
        "text": 3
    },
    "build_ms": 2,
    "items": [
        {
            "id": "p139.1",
            "order": 1,
            "type": "text",
            "bbox": {
                "l": 123.36,
                "t": 720.96,
                "r": 523.2,
                "b": 693.12
            },
            "text": "o Status: No funds have been transferred to state account. Funds will be transferred upon Board Approval."
        },
        {
            "id": "p139.2",
            "order": 2,
            "type": "heading",
            "bbox": {
                "l": 86.88,
                "t": 672,
                "r": 397.2,
                "b": 656.88
            },
            "text": "• Emergency Roof Repairs - Exum HPER Center",
            "attrs": {
                "block_label": "paragraph_title"
            },
            "level": 3
        },
        {
            "id": "p139.3",
            "order": 3,
            "type": "list",
            "bbox": {
                "l": 122.64,
                "t": 652.8,
                "r": 510,
                "b": 480
            },
            "text": "",
            "attrs": {
                "item_count": 7
            },
            "children": [
                {
                    "id": "p139.3.1",
                    "order": 4,
                    "type": "list_item",
                    "bbox": {
                        "l": 123.36,
                        "t": 652.8,
                        "r": 281.28,
                        "b": 637.68
                    },
                    "text": "o State Account No.: C8HZ"
                },
                {
                    "id": "p139.3.2",
                    "order": 5,
                    "type": "list_item",
                    "bbox": {
                        "l": 123.36,
                        "t": 631.44,
                        "r": 247.92,
                        "b": 616.32
                    },
                    "text": "o Fund Source: KSU"
                },
                {
                    "id": "p139.3.3",
                    "order": 6,
                    "type": "list_item",
                    "bbox": {
                        "l": 122.64,
                        "t": 609.84,
                        "r": 318,
                        "b": 594
                    },
                    "text": "o Appropriation: $250,000.00"
                },
                {
                    "id": "p139.3.4",
                    "order": 7,
                    "type": "list_item",
                    "bbox": {
                        "l": 123.12,
                        "t": 588.24,
                        "r": 295.68,
                        "b": 572.88
                    },
                    "text": "o Cash Balance: $230,650.00"
                },
                {
                    "id": "p139.3.5",
                    "order": 8,
                    "type": "list_item",
                    "bbox": {
                        "l": 122.88,
                        "t": 566.64,
                        "r": 504,
                        "b": 536.88
                    },
                    "text": "o Architectural Firm: Patrick D. Murphy Co. Architects, Louisville, Kentucky"
                },
                {
                    "id": "p139.3.6",
                    "order": 9,
                    "type": "list_item",
                    "bbox": {
                        "l": 123.6,
                        "t": 531.36,
                        "r": 486.24,
                        "b": 502.56
                    },
                    "text": "o Design Fees Allotment: $56,000.00. Construction Allotment: $194,000.00"
                },
                {
                    "id": "p139.3.7",
                    "order": 10,
                    "type": "list_item",
                    "bbox": {
                        "l": 123.12,
                        "t": 496.08,
                        "r": 510,
                        "b": 480
                    },
                    "text": "o Emergency Repairs Completed by Geoghegan Electrical: $19,350.00"
                }
            ]
        },
        {
            "id": "p139.4",
            "order": 11,
            "type": "text",
            "bbox": {
                "l": 122.88,
                "t": 474.24,
                "r": 540.72,
                "b": 387.6
            },
            "text": "o Status: A study has been prepared for this project; with an estimated cost of $1.5 million to replace the entire roof on the William Exum center. Project manager, Carl Kratzer with the Division of Engineering and Contract Administration (DECA), has been assigned to this project. Project on hold pending overall roofing study."
        },
        {
            "id": "p139.5",
            "order": 12,
            "type": "heading",
            "bbox": {
                "l": 86.88,
                "t": 377.28,
                "r": 299.04,
                "b": 361.92
            },
            "text": "• Hunter Hall Renovation Study",
            "attrs": {
                "block_label": "paragraph_title"
            },
            "level": 3
        },
        {
            "id": "p139.6",
            "order": 13,
            "type": "list",
            "bbox": {
                "l": 123.12,
                "t": 357.84,
                "r": 323.28,
                "b": 255.84
            },
            "text": "",
            "attrs": {
                "item_count": 5
            },
            "children": [
                {
                    "id": "p139.6.1",
                    "order": 14,
                    "type": "list_item",
                    "bbox": {
                        "l": 123.36,
                        "t": 357.84,
                        "r": 287.76,
                        "b": 342.72
                    },
                    "text": "o State Account No.: C8UH"
                },
                {
                    "id": "p139.6.2",
                    "order": 15,
                    "type": "list_item",
                    "bbox": {
                        "l": 123.12,
                        "t": 336.48,
                        "r": 301.92,
                        "b": 321.12
                    },
                    "text": "o Fund Source: Federal Funds"
                },
                {
                    "id": "p139.6.3",
                    "order": 16,
                    "type": "list_item",
                    "bbox": {
                        "l": 123.12,
                        "t": 315.12,
                        "r": 323.28,
                        "b": 299.28
                    },
                    "text": "o Appropriation: $1,900,000.00"
                },
                {
                    "id": "p139.6.4",
                    "order": 17,
                    "type": "list_item",
                    "bbox": {
                        "l": 123.12,
                        "t": 293.28,
                        "r": 285.6,
                        "b": 277.44
                    },
                    "text": "o Architectural Firm: TBD"
                },
                {
                    "id": "p139.6.5",
                    "order": 18,
                    "type": "list_item",
                    "bbox": {
                        "l": 123.36,
                        "t": 271.68,
                        "r": 304.56,
                        "b": 255.84
                    },
                    "text": "o Design Fees Allotment: TBD"
                }
            ]
        },
        {
            "id": "p139.7",
            "order": 19,
            "type": "text",
            "bbox": {
                "l": 122.64,
                "t": 250.08,
                "r": 535.44,
                "b": 151.92
            },
            "text": "o Status: This project has been initiated to determine if an elevator should be added and a covered walkway to connect to the Atwood facility. The funds will also be used to upgrade the electrical, plumbing and HVAC systems; as well as renovate classroom, research and meeting space. Project Manager, Butch Hatcher, with the Division of Engineering and Contract Administration (DECA) has been assigned to this project."
        },
        {
            "id": "p139.8",
            "order": 20,
            "type": "heading",
            "bbox": {
                "l": 87.12,
                "t": 142.8,
                "r": 307.44,
                "b": 126.96
            },
            "text": "Blazer Library Feasibility Study",
            "attrs": {
                "block_label": "paragraph_title"
            },
            "level": 3
        },
        {
            "id": "p139.9",
            "order": 21,
            "type": "list",
            "bbox": {
                "l": 123.12,
                "t": 123.12,
                "r": 283.92,
                "b": 64.8
            },
            "text": "",
            "attrs": {
                "item_count": 3
            },
            "children": [
                {
                    "id": "p139.9.1",
                    "order": 22,
                    "type": "list_item",
                    "bbox": {
                        "l": 123.36,
                        "t": 123.12,
                        "r": 283.92,
                        "b": 108.72
                    },
                    "text": "o State Account No.: C8K3"
                },
                {
                    "id": "p139.9.2",
                    "order": 23,
                    "type": "list_item",
                    "bbox": {
                        "l": 123.36,
                        "t": 101.76,
                        "r": 252.72,
                        "b": 86.64
                    },
                    "text": "o Fund Source: KSU"
                },
                {
                    "id": "p139.9.3",
                    "order": 24,
                    "type": "list_item",
                    "bbox": {
                        "l": 123.12,
                        "t": 80.16,
                        "r": 260.88,
                        "b": 64.8
                    },
                    "text": "o Appropriation: TBD"
                }
            ]
        }
    ],
    "excluded_furniture": {
        "first": [],
        "last": []
    }
}